ANGELINA US0059 (6451-37-001)

Items: 7

County: ANGELINA
Length: N/A
Highway: US0059
District: LUFKIN
Control Number: 6451-37-001
DBE Goal: N/A
Project: RMC - 645137001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $523,800.00
Date: 09/07/2023 (2 years ago)
Contract Number: N/A
Type: REFLECTIVE PAVEMENT MARKINGS (LONG LINE)
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (7)
E
Engineer's Estimate
$523,800.00
$399,400.00
Over/Under Est: -23.75% -$124,400.00
Over/Under Est: -9.97% -$52,236.00
Amt Left: 18.07% $72,164.00
Over/Under Est: -7.51% -$39,320.00
Amt Left: 21.3% $85,080.00
Delta: -2.74% -$12,916.00
Over/Under Est: 11.03% $57,780.00
Amt Left: 45.61% $182,180.00
Delta: -20.04% -$97,100.00
Over/Under Est: 12.49% $65,400.00
Amt Left: 47.52% $189,800.00
Delta: -1.31% -$7,620.00
Over/Under Est: 43.37% $227,160.00
Amt Left: 88.02% $351,560.00
Delta: -27.45% -$161,760.00
$809,200.00
Over/Under Est: 54.49% $285,400.00
Amt Left: 102.6% $409,800.00
Delta: -7.76% -$58,240.00

Bid Items & Bid Tabulations

7 Total 0 of 7
ANGELINA  |  US0059  |  LUFKIN  |  6451-37-001  |  09/07/2023  |  $523,800.00  |  RMC - 645137001  |  REFL PAVMT MRK (LONG LINE)  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BATTERSON, LLP
PROFESSIONAL TRAFFIC CONTROL LLC
TRP CONSTRUCTION GROUP, LLC
REYNOLDS & KAY, LTD.
INTERSTATE BARRICADES & MARKINGS, INC.
TRAFFIC HIGHWAY MAINTENANCE, LLC
STRIPE-A-ZONE, LLC
MOBILIZATION (CALLOUT)
EA 4.000 $1,000.000 $5,000.000 $1.000 $5,000.000 $3,600.000 $10,000.000 $6,500.000 $7,500.000
REFL PAV MRK TY II (W) 6" (BRK)
LF 50,000.000 $0.240 $0.180 $0.250 $0.270 $0.260 $0.240 $0.360 $0.360
REFL PAV MRK TY II (W) 6" (SLD)
LF 1,050,000.000 $0.220 $0.160 $0.200 $0.190 $0.240 $0.240 $0.310 $0.330
REFL PAV MRK TY II (W) 8" (SLD)
LF 8,000.000 $0.600 $0.300 $0.500 $0.360 $0.720 $0.400 $0.550 $0.650
REFL PAV MRK TY II (Y) 6" (BRK)
LF 100,000.000 $0.240 $0.180 $0.250 $0.280 $0.260 $0.230 $0.360 $0.360
REFL PAV MRK TY II (Y) 6" (SLD)
LF 1,100,000.000 $0.220 $0.160 $0.200 $0.200 $0.240 $0.230 $0.310 $0.330
TMA (MOBILE OPERATION)
DAY 60.000 $100.000 $100.000 $1.000 $10.000 $107.000 $100.000 $1.000 $175.000
Totals: $523,800.000 $399,400.000 $471,564.000 $484,480.000 $581,580.000 $589,200.000 $750,960.000 $809,200.000