County: ANGELINA Highway: US0059 Date: 08/03/2022 (2 years ago) Engineer's Estimate: $319,280 Control Number: 6411-51-001
Project: RMC - 641151001 District: LUFKIN Time: 365 CALENDAR DAYS Type: METAL BEAM GUARD FENCE REPAIR

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $319,280.00
ACE CONTRACTORS, INC.   $341,053.00 1
6.82% | $21,773.00
BK FIELD OPERATIONS LLC   $361,239.00 2
13.14% | $41,959.00
5.92% | $20,186.00
CROSS PLUS CONSTRUCTION, LLC   $387,605.00 3
21.4% | $68,325.00
13.65% | $46,552.00
7.30% | $26,366.00

Bid Items

Items: 33, 0 filtered
ANGELINA US0059  |  LUFKIN  |  6411-51-001  |  08/03/2022  |  $319,280  |  RMC - 641151001  |  METAL BEAM GUARD FENCE REPAIR  |  365 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate ACE CONTRACTORS, INC. BK FIELD OPERATIONS LLC CROSS PLUS CONSTRUCTION, LLC
429 6007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF 50.000 $165.000 $1.000 $500.000 $220.000
429 6009 CONC STR REPAIR (STANDARD) SF 25.000 $400.000 $500.000 $600.000 $550.000
500 6033 MOBILIZATION (CALLOUT) EA 10.000 $1,500.000 $1,500.000 $1.000 $2,200.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 1,800.000 $40.000 $40.000 $36.000 $50.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 2.000 $2,350.000 $2,000.000 $1,500.000 $4,400.000
540 6008 MTL BEAM GD FEN TRANS (T101) EA 2.000 $550.000 $1,500.000 $2,000.000 $4,400.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 1,800.000 $4.000 $4.000 $2.000 $6.000
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 1.000 $400.000 $200.000 $2,000.000 $110.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 2.000 $4,900.000 $4,500.000 $3,500.000 $4,400.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 1.000 $550.000 $1,000.000 $2,000.000 $110.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 4.000 $55.000 $50.000 $20.000 $110.000
770 6001 REPAIR RAIL ELEMENT (W - BEAM) LF 200.000 $19.000 $35.000 $30.000 $50.000
770 6010 REM / REPL TIMBER/STL POST W/O CONC FND EA 50.000 $95.000 $55.000 $80.000 $110.000
770 6011 REM / REPL TIMBER / STL POST W/CONC FND EA 85.000 $100.000 $75.000 $100.000 $110.000
770 6016 REPAIR STEEL POST WITH BASE PLATE EA 5.000 $130.000 $150.000 $80.000 $220.000
770 6019 REMOVE & REPLACE BLOCKOUT EA 100.000 $25.000 $30.000 $40.000 $28.000
770 6021 REPLACE SINGLE GDRAIL TERMINAL RAIL LF 100.000 $32.000 $60.000 $38.000 $28.000
770 6022 REPLACE SINGLE GDRAIL TERMINAL POST EA 5.000 $90.000 $100.000 $80.000 $110.000
770 6024 REPLACE TERMINAL ANCHOR POSTS EA 2.000 $130.000 $1.000 $100.000 $2,200.000
770 6027 REMOVE GDRAIL END TRT / REPL WITH SGT EA 15.000 $3,700.000 $5,500.000 $5,500.000 $3,300.000
770 6028 REPL SINGLE GDRAIL TERM IMPACT HEAD EA 2.000 $1,000.000 $1,250.000 $1,200.000 $2,200.000
770 6029 REM & RESET SGT IMPACT HEAD EA 2.000 $150.000 $200.000 $50.000 $1,650.000
770 6060 REMOVE AND REPLACE DAT EA 2.000 $2,000.000 $1,500.000 $1,600.000 $2,200.000
774 6001 REMOVE AND REPLACE (TRACC) EA 1.000 $20,000.000 $5,000.000 $28,000.000 $11,000.000
774 6002 REMOVE AND REPLACE (WIDE TRACC) EA 1.000 $15,500.000 $1.000 $25,000.000 $22,000.000
774 6010 REPAIR (REACT) EA 1.000 $4,600.000 $4,000.000 $6,000.000 $3,300.000
774 6014 REMOVE AND REPLACE (NARROW QUAD) EA 1.000 $17,000.000 $5,000.000 $23,000.000 $22,000.000
774 6027 REPAIR REACT (N) (CYLINDERS) EA 1.000 $5,800.000 $5,000.000 $3,500.000 $3,300.000
774 6028 REPAIR (QUAD) (N) (BAY) EA 5.000 $500.000 $3,000.000 $1,100.000 $1,925.000
774 6059 REPAIR (TRACC) (BAY) EA 10.000 $1,000.000 $2,500.000 $600.000 $220.000
776 6020 REPAIR (TY T101RC) LF 85.000 $50.000 $75.000 $85.000 $110.000
778 6001 CONCRETE RAIL REPAIR (IN-KIND) LF 25.000 $500.000 $750.000 $600.000 $440.000
6185 6002 TMA (STATIONARY) DAY 24.000 $500.000 $750.000 $1.000 $880.000
Totals: $319,280.00 $341,053.00 $361,239.00 $387,605.00