County: ANGELINA Highway: US0059 Date: 07/06/2022 (2 years ago) Engineer's Estimate: $262,350 Control Number: 6407-98-001
Project: RMC - 640798001 District: LUFKIN Time: 365 CALENDAR DAYS Type: TRAFFIC SIGNAL MAINTENANCE
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13
Plans

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $262,350.00
BAY CITY TRAFFIC   $242,776.99 1
-7.46% | -$19,573.01

Bid Items

Items: 44, 0 filtered
ANGELINA US0059  |  LUFKIN  |  6407-98-001  |  07/06/2022  |  $262,350  |  RMC - 640798001  |  TRAF SIGNAL MAINT  |  365 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate BAY CITY TRAFFIC
500 6033 MOBILIZATION (CALLOUT) EA 6.000 $1,000.000 $1,200.000
531 6001 CONC SIDEWALKS (4") SY 20.000 $65.000 $70.000
618 6046 CONDT (PVC) (SCH 80) (2") LF 150.000 $13.000 $11.000
618 6047 CONDT (PVC) (SCH 80) (2") (BORE) LF 300.000 $15.000 $12.000
618 6058 CONDT (PVC) (SCH 80) (4") LF 150.000 $25.000 $17.000
618 6059 CONDT (PVC) (SCH 80) (4") (BORE) LF 300.000 $30.000 $18.000
620 6007 ELEC CONDR (NO.8) BARE LF 1,500.000 $1.100 $1.000
620 6008 ELEC CONDR (NO.8) INSULATED LF 1,000.000 $1.400 $1.350
620 6010 ELEC CONDR (NO.6) INSULATED LF 300.000 $1.900 $1.650
624 6010 GROUND BOX TY D (162922)W/APRON EA 3.000 $670.000 $807.666
628 6002 REMOVE ELECTRICAL SERVICES EA 5.000 $450.000 $220.000
628 6188 ELC SRV TY D 120/240 070(NS)SS(E)SP(O) EA 3.000 $6,500.000 $6,200.000
628 6307 ELC SRV TY T 120/240 000(NS)GS(N)SP(O) EA 3.000 $4,500.000 $5,200.000
628 6309 ELC SRV TY T 120/240 000(NS)GS(N)TP(O) EA 3.000 $3,500.000 $2,500.000
682 6018 PED SIG SEC (LED)(COUNTDOWN) EA 20.000 $300.000 $470.000
682 6049 BACKPLATE W/REFL BRDR(4 SEC) EA 30.000 $130.000 $145.000
682 6050 BACKPLATE W/REFL BRDR(5 SEC) EA 15.000 $145.000 $160.000
682 6060 BACKPLATE W/REFL BRDR(3 SEC) EA 60.000 $90.000 $135.000
684 6028 TRF SIG CBL (TY A)(14 AWG)(2 CONDR) LF 2,000.000 $1.500 $1.350
684 6029 TRF SIG CBL (TY A)(14 AWG)(3 CONDR) LF 1,000.000 $1.800 $1.450
684 6030 TRF SIG CBL (TY A)(14 AWG)(4 CONDR) LF 2,000.000 $2.000 $1.750
684 6033 TRF SIG CBL (TY A)(14 AWG)(7 CONDR) LF 1,000.000 $3.000 $2.050
685 6001 INSTALL RDSD FLASH BEACON ASSEMBLY EA 5.000 $3,000.000 $3,200.000
690 6006 REMOVAL OF GROUND BOXES EA 5.000 $250.000 $200.000
690 6018 INSTALL OF SPAN CABLE ASSM LF 500.000 $2.000 $3.000
690 6025 REPLACE OF SIGNAL HEAD ASSM EA 50.000 $325.000 $225.000
690 6031 REPLACE OF PEDESTRIAN PUSH BUTTONS EA 8.000 $150.000 $150.000
690 6036 INSTALL OF FND FOR GROUND MNT CABINETS EA 4.000 $2,000.000 $1,800.000
690 6042 REPLACE OF CONTROL CABINET(POLE MNT) EA 1.000 $1,500.000 $1,200.000
690 6052 REPLACE OF SIGNAL POLE ASSM EA 4.000 $7,500.000 $8,000.000
690 6063 REMOVAL OF CONCRETE FOUNDATIONS EA 6.000 $700.000 $345.000
690 6071 INS OF TRF SIG PL FND (30" DRIL SHFT) LF 33.000 $265.000 $220.000
690 6072 INS OF TRF SIG PL FND (36" DRIL SHFT) LF 30.000 $335.000 $270.000
690 6087 INSTL PED POLE ASSM EA 3.000 $1,700.000 $1,650.000
690 6137 VIVDS CABLE (INSTALL) LF 1,500.000 $2.000 $1.000
6058 6001 BBU SYSTEM (EXTERNAL BATT CABINET) EA 4.000 $6,250.000 $6,250.000
6058 6003 REPLACE BBU BATTERIES EA 6.000 $2,100.000 $1,500.000
6185 6002 TMA (STATIONARY) DAY 20.000 $300.000 $300.000
7052 6044 LANE CLOSURE (SETUP AND REMOV)(TY 3) EA 2.000 $800.000 $225.000
7052 6050 LANE CLOSURE (SETUP AND REMOV)(TY 9) EA 2.000 $850.000 $227.500
7052 6053 LANE CLOSURE (SETUP AND REMOV)(TY 12) EA 2.000 $900.000 $262.000
7052 6061 LANE CLOSURE (MAINTENANCE) (TY 3) HR 8.000 $50.000 $75.000
7052 6067 LANE CLOSURE (MAINTENANCE) (TY 9) HR 8.000 $50.000 $75.000
7052 6070 LANE CLOSURE (MAINTENANCE) (TY 12) HR 8.000 $50.000 $75.000
Totals: $262,350.00 $242,777.00