REMOVING CONC (DRIVEWAYS)
|
SY
|
940.000
|
$24.000
|
$24.000
|
$23.000
|
$20.000
|
|
|
REMOVING CONC (CURB AND GUTTER)
|
LF
|
1,240.000
|
$15.000
|
$21.000
|
$10.000
|
$17.250
|
|
|
REMOVING STAB BASE & ASPH PAV (0"-10")
|
SY
|
1,559.000
|
$10.000
|
$15.000
|
$20.000
|
$20.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
2,132.000
|
$12.000
|
$41.550
|
$33.000
|
$23.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
1,195.000
|
$12.000
|
$42.000
|
$37.000
|
$20.000
|
|
|
BLADING
|
STA
|
24.140
|
$350.000
|
$1,565.000
|
$400.000
|
$200.000
|
|
|
BLOCK SODDING
|
SY
|
5,097.000
|
$5.250
|
$6.600
|
$7.000
|
$8.500
|
|
|
BROADCAST SEED (PERM) (RURAL) (CLAY)
|
SY
|
4,252.000
|
$0.200
|
$0.260
|
$0.220
|
$0.750
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
2,126.000
|
$0.200
|
$0.530
|
$0.210
|
$0.750
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
2,126.000
|
$0.200
|
$0.530
|
$0.190
|
$0.750
|
|
|
VEGETATIVE WATERING
|
MG
|
187.480
|
$25.000
|
$10.000
|
$37.000
|
$5.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY C)
|
SY
|
4,252.000
|
$2.000
|
$2.200
|
$1.600
|
$5.000
|
|
|
CEM TRT(PLNT MX) (CLN)(TYA)(GR1-2)(10")
|
SY
|
5,989.000
|
$35.000
|
$71.230
|
$89.000
|
$105.000
|
|
|
ASPH (RC-250)
|
TON
|
6.300
|
$1,800.000
|
$2,555.000
|
$1,750.000
|
$2,823.000
|
|
|
AGGR (TY E OR L, PE OR PL GR 4)
|
CY
|
131.000
|
$340.000
|
$324.000
|
$390.000
|
$375.000
|
|
|
AGGR (TY E OR L GR 5)
|
CY
|
43.000
|
$250.000
|
$570.000
|
$625.000
|
$450.000
|
|
|
ASPH (AC-15P OR CRS-2P)
|
TON
|
32.100
|
$1,300.000
|
$1,490.000
|
$1,250.000
|
$2,830.000
|
|
|
CEM STABIL BKFL
|
CY
|
139.000
|
$140.000
|
$227.000
|
$220.000
|
$250.000
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
20.000
|
$115.000
|
$115.000
|
$158.000
|
$250.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
35.000
|
$10.000
|
$10.000
|
$5.250
|
$20.000
|
|
|
CL C CONC (COLLAR)
|
EA
|
4.000
|
$1,200.000
|
$1,100.000
|
$890.000
|
$1,500.000
|
|
|
RIPRAP (CONC) (CL B) (6")
|
CY
|
230.000
|
$500.000
|
$622.000
|
$525.000
|
$525.000
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
30.000
|
$200.000
|
$196.000
|
$210.000
|
$180.000
|
|
|
RAIL (HANDRAIL)(TY E)
|
LF
|
86.000
|
$160.000
|
$166.000
|
$150.000
|
$250.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
270.000
|
$50.000
|
$60.000
|
$51.000
|
$70.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
518.000
|
$98.000
|
$94.000
|
$71.000
|
$95.000
|
|
|
INLET (COMPL)(TY A)
|
EA
|
1.000
|
$7,000.000
|
$7,150.000
|
$6,000.000
|
$10,000.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 18 IN)
|
EA
|
1.000
|
$6,000.000
|
$4,700.000
|
$4,700.000
|
$7,850.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 36 IN)
|
EA
|
1.000
|
$7,000.000
|
$8,250.000
|
$7,500.000
|
$10,000.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 48 IN)
|
EA
|
1.000
|
$16,000.000
|
$9,350.000
|
$10,500.000
|
$13,500.000
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (C)
|
EA
|
3.000
|
$700.000
|
$675.000
|
$675.000
|
$1,100.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
8.000
|
$750.000
|
$825.000
|
$800.000
|
$1,200.000
|
|
|
SET (TY II) (24 IN) (RCP) (3: 1) (P)
|
EA
|
1.000
|
$1,500.000
|
$1,300.000
|
$890.000
|
$1,500.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
12.000
|
$1,900.000
|
$1,425.000
|
$1,200.000
|
$1,800.000
|
|
|
CAST-IN-PLACE TRENCH DRAIN
|
LF
|
6.000
|
$600.000
|
$550.000
|
$525.000
|
$650.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
2.000
|
$1,600.000
|
$3,250.000
|
$1,050.000
|
$2,500.000
|
|
|
REMOV STR (PIPE)
|
EA
|
12.000
|
$370.000
|
$330.000
|
$220.000
|
$400.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$200,000.000
|
$250,000.000
|
$295,000.000
|
$225,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
16.000
|
$3,000.000
|
$1,600.000
|
$4,500.000
|
$2,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
306.000
|
$30.000
|
$38.500
|
$31.500
|
$45.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
306.000
|
$10.000
|
$10.000
|
$12.600
|
$10.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
81.000
|
$30.000
|
$24.000
|
$31.500
|
$15.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
81.000
|
$10.000
|
$10.000
|
$13.650
|
$1.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,636.000
|
$3.000
|
$3.300
|
$4.450
|
$4.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,636.000
|
$1.500
|
$1.100
|
$1.050
|
$1.500
|
|
|
CONC CURB & GUTTER (TY II)
|
LF
|
2,422.000
|
$40.000
|
$45.000
|
$23.000
|
$40.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
820.000
|
$95.000
|
$123.000
|
$95.000
|
$165.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
1,332.000
|
$35.000
|
$46.530
|
$50.000
|
$60.000
|
|
|
CONC SIDEWALKS (4")
|
SY
|
1,290.000
|
$75.000
|
$93.500
|
$68.000
|
$60.000
|
|
|
CURB RAMPS (TY 7)
|
EA
|
1.000
|
$1,500.000
|
$2,400.000
|
$3,150.000
|
$5,000.000
|
|
|
MAILBOX INSTALL-S (TIM-POST) TY 5
|
EA
|
4.000
|
$750.000
|
$550.000
|
$285.000
|
$750.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
1.000
|
$1,000.000
|
$1,155.000
|
$1,207.500
|
$1,200.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
|
EA
|
1.000
|
$1,200.000
|
$1,265.000
|
$1,370.250
|
$1,200.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
3.000
|
$360.000
|
$545.000
|
$449.400
|
$1,200.000
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
1.000
|
$600.000
|
$545.000
|
$588.000
|
$500.000
|
|
|
RELOCATE SM RD SN SUP&AM TY S80
|
EA
|
1.000
|
$700.000
|
$825.000
|
$900.900
|
$500.000
|
|
|
RELOCATE SM RD SN SUP&AM TY TWT
|
EA
|
5.000
|
$500.000
|
$435.000
|
$306.600
|
$500.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
1.000
|
$100.000
|
$104.000
|
$340.000
|
$400.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
15.000
|
$75.000
|
$82.000
|
$85.050
|
$75.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
4,828.000
|
$0.200
|
$1.100
|
$1.050
|
$1.500
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
4,828.000
|
$0.300
|
$1.100
|
$1.050
|
$1.500
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
120.000
|
$4.000
|
$6.600
|
$6.300
|
$10.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
776.000
|
$1.000
|
$1.300
|
$2.070
|
$5.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
244.000
|
$1.000
|
$1.300
|
$2.300
|
$5.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
760.000
|
$1.100
|
$1.100
|
$1.050
|
$1.500
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
480.000
|
$0.700
|
$2.200
|
$2.100
|
$3.250
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
1,348.000
|
$0.600
|
$1.650
|
$1.600
|
$2.250
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
4,826.000
|
$0.500
|
$1.650
|
$1.600
|
$2.250
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
50.000
|
$15.000
|
$16.500
|
$15.750
|
$22.500
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
6.000
|
$200.000
|
$230.000
|
$220.000
|
$400.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
6.000
|
$225.000
|
$285.000
|
$273.000
|
$425.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
62.000
|
$6.000
|
$6.600
|
$6.300
|
$10.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
60.000
|
$5.000
|
$6.600
|
$6.300
|
$10.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
666.000
|
$0.300
|
$1.100
|
$1.050
|
$1.500
|
|
|
RELOCATE RDSD FLASH BEACON ASSEMBLY
|
EA
|
1.000
|
$4,000.000
|
$8,250.000
|
$7,875.000
|
$4,000.000
|
|
|
SP MIXES SP-C PG70-22
|
TON
|
3,005.000
|
$170.000
|
$142.920
|
$160.000
|
$170.000
|
|
|
SP MIXES SP-C SAC-A PG70-22
|
TON
|
1,269.000
|
$170.000
|
$161.370
|
$165.000
|
$185.000
|
|
|
TACK COAT
|
GAL
|
2,648.000
|
$5.000
|
$5.000
|
$4.500
|
$6.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
3.000
|
$10,000.000
|
$15,000.000
|
$15,000.000
|
$11,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
171.000
|
$160.000
|
$50.000
|
$185.000
|
$175.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
7.000
|
$150.000
|
$50.000
|
$160.000
|
$500.000
|
|
Totals: |
$2,186,829.650
|
$2,637,474.140
|
$2,702,675.020
|
$2,950,488.300
|