Job Info for 0911-00-109

County: ANGELINA Highway: VA Date: 07/01/2021 (3 years ago) Engineer's Estimate: $4,952,509 Control Number: 0911-00-109
Project: F 2021(697) District: LUFKIN Time: 193 WORKING DAYS Type: HIGHWAY IMPROVEMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10
Plans

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $4,952,508.60
A. L. HELMCAMP, INC.   $4,639,696.67 1
-6.32% | -$312,811.93
DREWERY CONSTRUCTION COMPANY, INCORPORATED   $4,826,475.41 2
-2.54% | -$126,033.19
4.03% | $186,778.74
FNH CONSTRUCTION, LLC   $5,911,596.70 3
19.37% | $959,088.10
27.41% | $1,271,900.03
22.48% | $1,085,121.29
ALTUS CONSTRUCTION LLC   $6,151,421.86 4
24.21% | $1,198,913.26
32.58% | $1,511,725.19
4.06% | $239,825.16

Bid Items

Items: 16, 0 filtered
ANGELINA VA  |  LUFKIN  |  0911-00-109  |  07/01/2021  |  $4,952,509  |  F 2021(697)  |  HWY IMPRV  |  193 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate A. L. HELMCAMP, INC. DREWERY CONSTRUCTION COMPANY, INCORPORATED FNH CONSTRUCTION, LLC ALTUS CONSTRUCTION LLC
100 6002 PREPARING ROW STA 1,817.990 $1,800.000 $2,015.000 $1,750.000 $1,500.000 $2,108.880
164 6009 BROADCAST SEED (TEMP) (WARM) SY 318,848.000 $0.100 $0.070 $0.060 $0.200 $0.080
164 6011 BROADCAST SEED (TEMP) (COOL) SY 318,848.000 $0.100 $0.080 $0.060 $0.200 $0.080
164 6021 CELL FBR MLCH SEED(PERM)(RURAL)(SANDY) SY 763,980.000 $0.350 $0.360 $0.300 $0.500 $0.390
168 6001 VEGETATIVE WATERING MG 35,959.900 $10.000 $0.400 $12.000 $30.000 $1.320
169 6004 SOIL RETENTION BLANKETS (CL 1) (TY D) SY 10,939.000 $3.000 $1.040 $0.750 $6.500 $0.980
500 6001 MOBILIZATION LS 1.000 $450,000.000 $190,000.000 $450,000.000 $585,000.000 $609,186.110
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 39.000 $1,500.000 $2,500.000 $6,500.000 $8,500.000 $21,672.630
506 6001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 3,300.000 $35.000 $27.000 $15.000 $30.000 $41.040
506 6011 ROCK FILTER DAMS (REMOVE) LF 3,300.000 $10.000 $8.000 $3.000 $15.000 $12.420
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 1,668.000 $25.000 $15.000 $10.000 $40.000 $30.750
506 6024 CONSTRUCTION EXITS (REMOVE) SY 1,668.000 $10.000 $4.000 $5.000 $20.000 $10.490
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 43,667.000 $3.000 $2.400 $1.950 $4.000 $2.830
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 43,667.000 $1.000 $0.500 $0.350 $2.000 $0.900
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $10,000.000 $10,000.000 $14,500.000 $16,500.000 $6,621.590
6185 6002 TMA (STATIONARY) DAY 186.000 $250.000 $250.000 $110.000 $350.000 $186.010
Totals: $4,952,508.60 $4,639,696.67 $4,826,475.41 $5,911,596.70 $6,151,421.87