ANGELINA VA (0911-00-107)

Items: 36

County: ANGELINA
Length: N/A
Highway: VA
District: LUFKIN
Control Number: 0911-00-107
DBE Goal: N/A
Project: STP 2B20(053)HES
Guaranty: N/A
Time: 495 WORKING DAYS
Engineer's Estimate: $3,770,972.90
Date: 08/05/2020 (5 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$3,770,972.90
1
$3,456,090.05
Over/Under Est: -8.35% -$314,882.85
Over/Under Est: 1.7% $64,062.32
Amt Left: 10.96% $378,945.17
Over/Under Est: 4.86% $183,370.89
Amt Left: 14.42% $498,253.74
Delta: -3.11% -$119,308.57
$3,985,737.30
Over/Under Est: 5.7% $214,764.40
Amt Left: 15.33% $529,647.25
Delta: -0.79% -$31,393.51
$4,373,750.25
Over/Under Est: 15.98% $602,777.35
Amt Left: 26.55% $917,660.20
Delta: -9.74% -$388,012.95
$5,581,311.75
Over/Under Est: 48.01% $1,810,338.85
Amt Left: 61.49% $2,125,221.70
Delta: -27.61% -$1,207,561.50
$5,615,286.90
Over/Under Est: 48.91% $1,844,314.00
Amt Left: 62.48% $2,159,196.85
Delta: -0.61% -$33,975.15

Bid Items & Bid Tabulations

36 Total 0 of 36
ANGELINA  |  VA  |  LUFKIN  |  0911-00-107  |  08/05/2020  |  $3,770,972.90  |  STP 2B20(053)HES  |  HAZARD ELIM & SAFETY  |  495 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
3LW CIVIL LLC
A R BROTHERS CONSTRUCTION SERVICES, INC.
EAST TEXAS BRIDGE, INC.
FNH CONSTRUCTION, LLC
HJC FARMS, INC.
DBI SERVICES, LLC
ALTUS CONSTRUCTION LLC
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 3,011.000 $15.000 $7.000 $23.000 $30.000 $30.000 $25.000 $50.000 $54.960
BLADING
STA 10.000 $1,500.000 $75.000 $156.000 $1,000.000 $450.000 $175.000 $300.000 $1,374.110
BROADCAST SEED (TEMP) (WARM)
SY 19,052.000 $0.300 $0.150 $0.280 $0.310 $0.500 $1.000 $1.000 $0.380
BROADCAST SEED (TEMP) (COOL)
SY 19,052.000 $0.300 $0.150 $0.280 $0.310 $0.500 $1.000 $1.000 $0.370
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 32,392.000 $1.000 $0.450 $0.450 $0.550 $0.500 $1.000 $1.500 $0.620
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 5,712.000 $1.000 $0.450 $0.470 $0.550 $0.500 $1.000 $1.500 $0.650
VEGETATIVE WATERING
MG 1,524.160 $20.000 $10.000 $19.560 $20.000 $30.000 $50.000 $75.000 $34.350
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 32,139.000 $2.000 $0.800 $0.780 $0.900 $4.000 $1.750 $4.000 $1.070
SOIL RETENTION BLANKETS (CL 1) (TY D)
SY 5,702.000 $2.000 $0.800 $0.780 $0.900 $5.000 $1.750 $4.000 $1.070
D-GR HMA(SQ) TY-D PG64-22 NON-MOW STRIP
SY 20,903.000 $55.000 $60.000 $70.000 $60.000 $40.000 $60.000 $94.000 $82.450
RIPRAP (MOW STRIP)(4 IN)
CY 26.000 $425.000 $500.000 $507.000 $600.000 $550.000 $700.000 $500.000 $1,030.580
MOBILIZATION
LS 1.000 $300,000.000 $100,000.000 $370,000.000 $350,000.000 $398,000.000 $350,000.000 $425,000.000 $556,513.620
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 42.000 $2,000.000 $9,000.000 $3,600.000 $7,000.000 $6,000.000 $3,500.000 $10,000.000 $13,741.080
TEMP SEDMT CONT FENCE (INSTALL)
LF 8,660.000 $2.000 $0.500 $2.730 $3.000 $4.000 $6.000 $3.000 $4.810
TEMP SEDMT CONT FENCE (REMOVE)
LF 8,660.000 $1.000 $0.500 $1.360 $1.300 $2.000 $1.000 $1.000 $2.750
MTL W-BEAM GD FEN (TIM POST)
LF 30,987.500 $25.000 $20.720 $17.830 $19.000 $21.000 $25.000 $25.000 $26.510
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 57.000 $1,540.000 $1,300.000 $1,494.000 $1,500.000 $1,850.000 $2,000.000 $2,500.000 $1,903.140
MTL BEAM GD FEN TRANS (T101)
EA 8.000 $1,200.000 $750.000 $731.000 $800.000 $1,850.000 $1,500.000 $1,700.000 $1,670.910
MTL BEAM GD FEN TRANS (T6)
EA 3.000 $1,000.000 $500.000 $453.000 $500.000 $1,850.000 $1,250.000 $1,700.000 $1,242.190
SHORT RADIUS
LF 52.000 $25.000 $37.000 $40.000 $45.000 $50.000 $45.000 $100.000 $61.830
DRIVEWAY TERMINAL ANCHOR SECTION
EA 2.000 $1,000.000 $875.000 $1,046.000 $1,100.000 $1,850.000 $1,500.000 $2,100.000 $1,374.110
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 3.000 $1,000.000 $1,100.000 $975.000 $1,100.000 $1,850.000 $1,500.000 $2,250.000 $1,374.110
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 650.000 $25.000 $20.000 $20.000 $22.000 $185.000 $25.000 $50.000 $31.600
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 326.000 $85.000 $60.000 $60.000 $65.000 $55.000 $60.000 $75.000 $103.060
MTL BM GD FEN TRANS (31"-28")
EA 33.000 $700.000 $400.000 $393.000 $415.000 $600.000 $600.000 $2,000.000 $845.080
MTL BM GD FEN TRANS (ANCHOR PLATE)
EA 27.000 $850.000 $600.000 $505.000 $535.000 $900.000 $625.000 $2,250.000 $845.080
REMOVE METAL BEAM GUARD FENCE
LF 33,855.000 $2.000 $1.750 $3.000 $2.250 $3.000 $3.000 $1.750 $1.370
REMOVE TERMINAL ANCHOR SECTION
EA 855.000 $150.000 $150.000 $228.000 $165.000 $200.000 $300.000 $100.000 $230.850
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 1.000 $250.000 $200.000 $228.000 $165.000 $500.000 $300.000 $600.000 $412.230
RM MTL BM GD FEN TRANS (T101)
EA 8.000 $300.000 $100.000 $157.000 $165.000 $500.000 $300.000 $600.000 $412.230
GUARDRAIL END TREATMENT (INSTALL)
EA 233.000 $2,600.000 $2,200.000 $2,328.000 $2,500.000 $2,650.000 $3,000.000 $2,900.000 $3,304.730
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 1.000 $25,000.000 $26,000.000 $29,728.000 $35,000.000 $25,000.000 $30,000.000 $34,300.000 $34,352.690
CRASH CUSH ATTEN (INSTL)(R)(W)(TL3)
EA 1.000 $2,500.000 $28,000.000 $31,038.000 $45,000.000 $35,000.000 $40,000.000 $46,800.000 $43,971.450
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 504.000 $25.000 $20.000 $28.000 $30.000 $50.000 $40.000 $30.000 $40.470
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $10,000.000 $4,194.000 $55,000.000 $16,500.000 $10,000.000 $7,200.000 $10,305.810
TMA (STATIONARY)
DAY 457.000 $325.000 $75.000 $20.000 $100.000 $250.000 $200.000 $300.000 $343.530
Totals: $3,770,972.900 $3,456,090.050 $3,835,035.235 $3,954,343.790 $3,985,737.300 $4,373,750.250 $5,581,311.750 $5,615,286.911