ANGELINA VA (0911-00-107)
Items: 36
County: ANGELINA
Length: N/A
Highway: VA
District: LUFKIN
Control Number: 0911-00-107
DBE Goal: N/A
Project: STP 2B20(053)HES
Guaranty: N/A
Time: 495 WORKING DAYS
Engineer's Estimate: $3,770,972.90
Date: 08/05/2020 (5 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,770,972.90 | |||
| $3,456,090.05 |
-8.35%
-$314,882.85
|
|||
| $3,835,035.22 |
1.7%
$64,062.32
|
10.96%
$378,945.17
|
||
| $3,954,343.79 |
4.86%
$183,370.89
|
14.42%
$498,253.74
|
-3.11%
-$119,308.57
|
|
| $3,985,737.30 |
5.7%
$214,764.40
|
15.33%
$529,647.25
|
-0.79%
-$31,393.51
|
|
| $4,373,750.25 |
15.98%
$602,777.35
|
26.55%
$917,660.20
|
-9.74%
-$388,012.95
|
|
| $5,581,311.75 |
48.01%
$1,810,338.85
|
61.49%
$2,125,221.70
|
-27.61%
-$1,207,561.50
|
|
| $5,615,286.90 |
48.91%
$1,844,314.00
|
62.48%
$2,159,196.85
|
-0.61%
-$33,975.15
|
E
Engineer's Estimate
$3,770,972.90
1
Awarded
$3,456,090.05
Over/Under Est:
-8.35%
-$314,882.85
$3,835,035.22
Over/Under Est:
1.7%
$64,062.32
Amt Left:
10.96%
$378,945.17
$3,954,343.79
Over/Under Est:
4.86%
$183,370.89
Amt Left:
14.42%
$498,253.74
Delta:
-3.11%
-$119,308.57
$3,985,737.30
Over/Under Est:
5.7%
$214,764.40
Amt Left:
15.33%
$529,647.25
Delta:
-0.79%
-$31,393.51
$4,373,750.25
Over/Under Est:
15.98%
$602,777.35
Amt Left:
26.55%
$917,660.20
Delta:
-9.74%
-$388,012.95
$5,581,311.75
Over/Under Est:
48.01%
$1,810,338.85
Amt Left:
61.49%
$2,125,221.70
Delta:
-27.61%
-$1,207,561.50
$5,615,286.90
Over/Under Est:
48.91%
$1,844,314.00
Amt Left:
62.48%
$2,159,196.85
Delta:
-0.61%
-$33,975.15
Bid Items & Bid Tabulations
36
Total
0 of 36