Job Info for 0911-00-095

County: ANGELINA Highway: VA Date: 02/01/2023 (1 year ago) Engineer's Estimate: $3,604,870 Control Number: 0911-00-095
Project: C 911-00-95 District: LUFKIN Time: 122 WORKING DAYS Type: HIGHWAY IMPROVEMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,604,870.46
CENTERLINE TECHNOLOGIES, LLC   $3,368,123.02 1
-6.57% | -$236,747.44
INTERSTATE BARRICADES & MARKINGS, INC.   $3,554,650.24 2
-1.39% | -$50,220.22
5.54% | $186,527.22
TRP CONSTRUCTION GROUP, LLC   $3,835,985.78 3
6.41% | $231,115.32
13.89% | $467,862.76
7.91% | $281,335.54
STRIPE-A-ZONE, LLC   $3,877,812.33 4
7.57% | $272,941.87
15.13% | $509,689.31
1.09% | $41,826.55
BATTERSON, LLP   $4,098,729.16 5
13.7% | $493,858.70
21.69% | $730,606.14
5.70% | $220,916.83
Subcontractor Percentage Amount
SURFACE PREPARATION TECHNOLOGIES, LLC 1.01% $34,018.04
Total: 1.01% $34,018.04

Bid Items

Items: 16, 0 filtered
ANGELINA VA  |  LUFKIN  |  0911-00-095  |  02/01/2023  |  $3,604,870  |  C 911-00-95  |  HWY IMPRV  |  122 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate CENTERLINE TECHNOLOGIES, LLC INTERSTATE BARRICADES & MARKINGS, INC. TRP CONSTRUCTION GROUP, LLC STRIPE-A-ZONE, LLC BATTERSON, LLP
500 6001 MOBILIZATION LS 1.000 $171,200.000 $1.000 $30,000.000 $80,000.000 $50,000.000 $220,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 9.000 $1,000.000 $1.000 $2,000.000 $3,000.000 $500.000 $9,500.000
533 6002 RUMBLE STRIPS (CENTERLINE) LF 119,053.000 $0.200 $0.300 $0.250 $0.260 $0.340 $0.240
666 6035 REFL PAV MRK TY I (W)8"(SLD)(090MIL) LF 245.000 $1.050 $1.000 $0.850 $3.000 $1.500 $2.000
666 6285 REF PROF PAV MRK TY I(W)6"(SLD)(090MIL) LF 2,223,156.000 $0.650 $0.690 $0.720 $0.760 $0.760 $0.790
666 6289 REF PROF PAV MRK TY I(Y)6"(SLD)(090MIL) LF 1,910,963.000 $0.700 $0.690 $0.720 $0.750 $0.760 $0.790
666 6293 REF PROF PAV MRK TY I(Y)6"(BRK)(090MIL) LF 126,125.000 $1.000 $0.690 $0.720 $0.980 $0.780 $0.790
666 6305 RE PM W/RET REQ TY I (W)6"(BRK)(090MIL) LF 16,320.000 $0.550 $0.440 $0.440 $0.560 $0.560 $0.420
666 6308 RE PM W/RET REQ TY I (W)6"(SLD)(090MIL) LF 267,570.000 $0.480 $0.440 $0.440 $0.510 $0.550 $0.420
666 6317 RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL) LF 24,697.000 $0.550 $0.440 $0.440 $0.560 $0.560 $0.420
666 6320 RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL) LF 415,467.000 $0.480 $0.440 $0.440 $0.510 $0.550 $0.420
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 621.000 $15.000 $15.000 $12.000 $16.000 $14.000 $10.000
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 1.000 $230.000 $500.000 $250.000 $500.000 $300.000 $200.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 1.000 $300.000 $500.000 $300.000 $500.000 $350.000 $220.000
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 14,098.000 $5.000 $4.500 $5.850 $4.850 $9.500 $4.500
6185 6005 TMA (MOBILE OPERATION) DAY 244.000 $250.000 $1.000 $1.000 $1.000 $1.000 $100.000
Totals: $3,604,870.46 $3,368,123.02 $3,554,650.24 $3,835,985.78 $3,877,812.33 $4,098,729.16