County: ANGELINA Highway: VA Date: 10/02/2018 (6 years ago) Engineer's Estimate: $1,339,333 Control Number: 0911-00-078
Project: C 911-00-78 District: LUFKIN Time: 118 WORKING DAYS Type: INSTALL PROFILE PAVEMENT MARKINGS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,339,332.60
PMI PAVEMENT MARKING, INC.   $1,368,036.18 1
2.14% | $28,703.58
STRIPE-A-ZONE, INC.   $1,562,072.76 2
16.63% | $222,740.16
14.18% | $194,036.58
INTERSTATE BARRICADES & MARKINGS, INC.   $1,578,986.50 3
17.89% | $239,653.90
15.42% | $210,950.32
1.08% | $16,913.74
STRIPING TECHNOLOGY, L.P.   $1,980,862.80 4
47.9% | $641,530.20
44.8% | $612,826.62
25.45% | $401,876.30
TRP CONSTRUCTION GROUP, LLC   $1,990,935.88 5
48.65% | $651,603.28
45.53% | $622,899.70
0.51% | $10,073.08
TOTAL HIGHWAY MAINTENANCE, LLC   $2,535,632.44 6
89.32% | $1,196,299.84
85.35% | $1,167,596.26
27.36% | $544,696.56

Bid Items

Items: 12, 0 filtered
ANGELINA VA  |  LUFKIN  |  0911-00-078  |  10/02/2018  |  $1,339,333  |  C 911-00-78  |  INSTL PROFILE PAVMT MRK  |  118 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate PMI PAVEMENT MARKING, INC. STRIPE-A-ZONE, INC. INTERSTATE BARRICADES & MARKINGS, INC. STRIPING TECHNOLOGY, L.P. TRP CONSTRUCTION GROUP, LLC TOTAL HIGHWAY MAINTENANCE, LLC
500 6001 MOBILIZATION LS 1.000 $69,440.000 $20,000.000 $17,500.000 $20,000.000 $10,000.000 $75,000.000 $100,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 8.000 $2,000.000 $500.000 $500.000 $100.000 $7,000.000 $500.000 $4,500.000
666 6035 REFL PAV MRK TY I (W)8"(SLD)(090MIL) LF 10,788.000 $0.500 $0.500 $1.000 $0.600 $0.650 $0.710 $0.840
666 6283 REF PROF PAV MRK TY I(W)4"(SLD)(090MIL) LF 1,311,345.000 $0.350 $0.380 $0.445 $0.430 $0.550 $0.550 $0.670
666 6287 REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL) LF 1,819,621.000 $0.350 $0.380 $0.445 $0.450 $0.550 $0.550 $0.670
666 6291 REF PROF PAV MRK TY I(Y)4"(BRK)(090MIL) LF 167,670.000 $0.350 $0.380 $0.475 $0.450 $0.600 $0.600 $0.850
666 6299 RE PM W/RET REQ TY I (W)4"(BRK)(090MIL) LF 13,220.000 $0.200 $0.250 $0.310 $0.280 $0.330 $0.340 $0.470
666 6302 RE PM W/RET REQ TY I (W)4"(SLD)(090MIL) LF 38,420.000 $0.200 $0.250 $0.260 $0.280 $0.330 $0.300 $0.410
666 6311 RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL) LF 920.000 $0.200 $0.250 $1.000 $0.280 $1.000 $0.340 $1.000
666 6314 RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL) LF 66,170.000 $0.200 $0.250 $0.270 $0.280 $0.330 $0.300 $0.410
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 6,910.000 $3.000 $8.000 $3.185 $4.000 $6.000 $6.550 $7.350
6185 6005 TMA (MOBILE OPERATION) DAY 198.000 $250.000 $1.000 $10.000 $165.000 $20.000 $1.000 $250.000
Totals: $1,339,332.60 $1,368,036.18 $1,562,072.77 $1,578,986.50 $1,980,862.80 $1,990,935.88 $2,535,632.44