Show Job Controls
Bid Cobra

ANGELINA BU 59-G (0176-02-125)

Items: 76

County: ANGELINA
Length: N/A
Highway: BU 59-G
District: LUFKIN
Control Number: 0176-02-125
DBE Goal: N/A
Project: F 2022(895)
Guaranty: N/A
Time: 95 WORKING DAYS
Engineer's Estimate: $1,116,132.60
Date: 08/04/2022 (3 years ago)
Contract Number: N/A
Type: BICYCLE AND PEDESTRIAN IMPROVEMENTS
Mail/Deliver Bids To: N/A
JESSE SISCO
PRAVEEN RAMANATHAN
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$1,116,132.60
$1,363,053.76
Over/Under Est: 22.12% $246,921.16
$1,449,934.00
Over/Under Est: 29.91% $333,801.40
Amt Left: 6.37% $86,880.24
$1,528,390.10
Over/Under Est: 36.94% $412,257.50
Amt Left: 12.13% $165,336.34
Delta: -5.41% -$78,456.10
Over/Under Est: 49.72% $554,981.93
Amt Left: 22.6% $308,060.77
Delta: -9.34% -$142,724.43

Bid Items & Bid Tabulations

76 Total 0 of 76
ANGELINA  |  BU 59-G  |  LUFKIN  |  0176-02-125  |  08/04/2022  |  $1,116,132.60  |  F 2022(895)  |  BICYCLE AND PEDESTRIAN IMPRVS  |  95 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ENCINO LANDSCAPE, INC.
FNH CONSTRUCTION, LLC
TI-ZACK CONCRETE, INC.
PROJECT ALLIED RESOURCES, LLC
PREP ROW (TREE)(LESS THAN 24" DIA)
EA 19.000 $250.000 $1,000.000 $3,500.000 $1,100.000 $838.000
REMOVING CONC (DRIVEWAYS)
SY 2,263.000 $20.000 $20.000 $20.000 $21.000 $34.200
REMOVING CONC (CURB)
LF 649.000 $20.000 $20.000 $15.000 $7.000 $10.900
REMOVING CONC (CURB AND GUTTER)
LF 2,335.000 $15.000 $20.000 $15.000 $6.000 $18.700
REMOVING CONC (SIDEWALK OR RAMP)
SY 49.000 $20.000 $20.000 $20.000 $20.000 $30.500
REMOVING CONC (PAVERS)
SY 34.000 $20.000 $20.000 $20.000 $28.000 $15.900
REMOVING STAB BASE & ASPH PAV (0"-10")
SY 1,622.000 $15.000 $20.000 $20.000 $30.000 $16.600
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 20.000 $150.000 $1.000 $250.000 $55.000 $80.000
FURNISHING AND PLACING TOPSOIL (4")
SY 1,531.000 $2.000 $1.000 $10.000 $3.000 $0.890
BLOCK SODDING
SY 1,531.000 $5.000 $1.000 $10.000 $3.000 $13.100
BROADCAST SEED (TEMP) (COOL)
SY 1,531.000 $0.200 $0.150 $2.000 $1.000 $0.610
VEGETATIVE WATERING
MG 61.000 $10.000 $5.000 $50.000 $11.000 $80.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 779.000 $50.000 $80.000 $100.000 $110.000 $80.000
DRILL SHAFT (24 IN)
LF 36.000 $200.000 $300.000 $300.000 $248.000 $163.000
CL C CONC (RAIL FOUNDATION)
CY 1.400 $800.000 $800.000 $2,000.000 $5,367.000 $1,030.000
RIPRAP (CONC)(4 IN)
CY 30.000 $500.000 $500.000 $550.000 $1,149.000 $987.000
RIPRAP (MOW STRIP)(4 IN)
CY 2.000 $500.000 $500.000 $550.000 $1,149.000 $995.000
RETROFIT RAIL (TY C402)
LF 53.300 $305.000 $350.000 $185.000 $198.000 $342.000
RETROFIT RAIL (TY PR11)
LF 63.300 $175.000 $300.000 $185.000 $187.000 $274.000
INLET (COMP) (TY SIDEWALK BRIDGE)
EA 1.000 $8,000.000 $12,000.000 $12,500.000 $21,934.000 $18,500.000
ADJUSTING MANHOLES
EA 2.000 $790.000 $800.000 $3,000.000 $2,394.000 $2,400.000
ADJUSTING MANHOLES & INLETS
EA 1.000 $1,500.000 $2,000.000 $5,000.000 $2,394.000 $2,400.000
ADJUSTING MANHOLES (WATER METER)
EA 3.000 $300.000 $500.000 $850.000 $1,596.000 $663.000
ADJUSTING MANHOLES (ELECTRIC BOX)
EA 1.000 $500.000 $500.000 $850.000 $2,394.000 $885.000
REMOVE STR (RAIL)
LF 44.800 $15.000 $60.000 $50.000 $61.000 $51.000
MOBILIZATION
LS 1.000 $100,000.000 $111,111.110 $140,000.000 $78,446.000 $150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $4,000.000 $10,000.000 $8,500.000 $1,650.000 $7,940.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,050.000 $2.000 $3.000 $4.000 $0.100 $7.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,050.000 $1.000 $0.500 $2.000 $0.100 $1.710
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 86.000 $3.500 $3.000 $18.000 $6.000 $12.100
BIODEG EROSN CONT LOGS (REMOVE)
LF 86.000 $1.000 $0.500 $9.000 $6.000 $3.340
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 620.000 $75.000 $100.000 $85.000 $75.000 $95.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 80.000 $75.000 $100.000 $85.000 $73.000 $91.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 620.000 $25.000 $20.000 $20.000 $6.000 $11.500
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 80.000 $22.500 $20.000 $20.000 $6.000 $11.200
COLORED TEXTURED CONC (4")
SY 295.000 $80.000 $150.000 $100.000 $151.000 $93.000
CONC CURB & GUTTER (TY II)
LF 2,335.000 $35.000 $25.000 $50.000 $54.000 $55.000
DRIVEWAYS (CONC)
SY 2,175.000 $85.000 $80.000 $80.000 $120.000 $122.000
DRIVEWAYS (ACP)
SY 1,588.000 $35.000 $80.000 $50.000 $99.000 $77.000
CONC SIDEWALKS (5")
SY 2,888.000 $75.000 $80.000 $60.000 $120.000 $98.000
CURB RAMPS (TY 1)
EA 1.000 $1,500.000 $2,000.000 $3,000.000 $1,853.000 $5,170.000
CURB RAMPS (TY 6)
EA 1.000 $2,000.000 $2,000.000 $3,000.000 $3,117.000 $6,140.000
CURB RAMPS (TY 10)
EA 1.000 $1,100.000 $2,000.000 $3,000.000 $3,117.000 $5,610.000
SHORT RADIUS
LF 25.000 $50.000 $200.000 $85.000 $110.000 $136.000
MTL BEAM GD FEN TRANS(THRIE BEAM)28"
EA 1.000 $2,300.000 $2,000.000 $2,500.000 $2,552.000 $3,100.000
REMOVE METAL BEAM GUARD FENCE
LF 100.000 $3.000 $5.000 $5.000 $1.000 $3.340
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $150.000 $500.000 $500.000 $198.000 $335.000
CHAIN LINK FENCE (REMOVE)
LF 67.000 $3.000 $20.000 $25.000 $9.000 $9.200
CONDT (PVC) (SCH 40) (2")
LF 80.000 $14.000 $20.000 $20.000 $22.000 $26.200
CONDT (PVC) (SCH 80) (2") (BORE)
LF 139.000 $22.000 $60.000 $65.000 $55.000 $59.000
ELEC CONDR (NO.8) BARE
LF 292.000 $1.500 $2.000 $3.000 $11.000 $2.160
GROUND BOX TY A (122311)W/APRON
EA 4.000 $750.000 $1,000.000 $1,500.000 $1,650.000 $1,790.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $600.000 $800.000 $1,000.000 $550.000 $895.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $745.000 $800.000 $1,000.000 $550.000 $1,020.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 2.000 $430.000 $800.000 $1,000.000 $550.000 $557.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $600.000 $500.000 $850.000 $550.000 $741.000
REMOVE SM RD SN SUP&AM
EA 5.000 $100.000 $200.000 $350.000 $55.000 $154.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 50.000 $1.000 $2.000 $6.000 $6.000 $11.500
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 372.000 $13.250 $20.000 $20.000 $22.000 $24.900
ELIM EXT PAV MRK & MRKS (4")
LF 48.000 $0.300 $1.000 $2.000 $6.000 $1.560
ELIM EXT PAV MRK & MRKS (8")
LF 50.000 $0.800 $1.000 $5.000 $6.000 $3.450
ELIM EXT PAV MRK & MRKS (24")
LF 36.000 $2.200 $5.000 $20.000 $6.000 $15.200
ELIM EXT PAV MRK & MRKS (ARROW)
EA 1.000 $33.000 $100.000 $250.000 $165.000 $269.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 1.000 $40.000 $100.000 $250.000 $165.000 $292.000
PAV SURF PREP FOR MRK (8")
LF 100.000 $0.150 $0.500 $6.000 $6.000 $0.560
PAV SURF PREP FOR MRK (24")
LF 372.000 $5.000 $5.000 $20.000 $6.000 $5.300
PAV SURF PREP FOR MRK (ARROW)
EA 1.000 $55.000 $50.000 $250.000 $165.000 $96.000
PAV SURF PREP FOR MRK (WORD)
EA 1.000 $100.000 $100.000 $250.000 $165.000 $165.000
PED SIG SEC (LED)(COUNTDOWN)
EA 7.000 $530.000 $900.000 $2,250.000 $1,100.000 $411.000
TRF SIG CBL (TY A)(12 AWG)(2 CONDR)
LF 484.000 $1.750 $2.000 $4.000 $6.000 $2.070
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
LF 519.000 $2.200 $4.000 $4.000 $7.000 $3.290
PED POLE ASSEMBLY
EA 6.000 $2,000.000 $2,500.000 $2,250.000 $2,200.000 $1,520.000
PED DETECT PUSH BUTTON (APS)
EA 7.000 $1,000.000 $1,000.000 $1,850.000 $1,650.000 $1,270.000
D-GR HMA TY-D PG64-22
TON 12.000 $180.000 $200.000 $500.000 $440.000 $442.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $7,500.000 $8,999.000 $12,500.000 $1.000 $9,020.000
TMA (STATIONARY)
DAY 95.000 $175.000 $250.000 $250.000 $1.000 $337.000
Totals: $1,116,132.600 $1,363,053.760 $1,449,934.000 $1,528,390.100 $1,671,114.530