Show Job Controls
Bid Cobra

ANDREWS SH 115 (0354-06-030)

Items: 117

County: ANDREWS
Length: N/A
Highway: SH 115
District: ODESSA
Control Number: 0354-06-030
DBE Goal: N/A
Project: STP 2022(582)HES
Guaranty: N/A
Time: 640 WORKING DAYS
Engineer's Estimate: $29,597,171.59
Date: 08/04/2022 (3 years ago)
Contract Number: N/A
Type: CONSTRUCT BRIDGE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$29,597,171.59
$36,740,466.75
Over/Under Est: 24.14% $7,143,295.16
Over/Under Est: 28.24% $8,356,787.26
Amt Left: 3.3% $1,213,492.10
Subcontractor Percentage Amount
MAKIN' IT MOVE TRANSPORT,LLC 3.38% $1,336,903.70
WILLIS ELECTRIC CO., LP 2.46% $973,012.76
DOUBLE A CONTRACTING, L.P. 0.90% $355,980.28
PEYSON TRANSPORT, LLC 0.68% $268,962.88
LONE STAR EROSION CONTROL 0.61% $241,275.52
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. 0.58% $229,409.51
HB FARMER FOUNDATION, LLC 0.54% $213,588.17
DUSTROL, INC. 0.46% $181,945.47
DK CONTRACTING, LLC 0.31% $122,615.43
1 PRIORITY ENVIRONMENTAL SERVICES, LLC 0.26% $102,838.75
STERLING CRANE LLC 0.14% $55,374.71
BROADHEAD BORING LLC 0.09% $35,598.03
FIBERTEX, LLC 0.04% $15,821.35
TEXAS CUTTING & CORING GP, INC. 0.03% $11,866.01
TEJAS CONCRETE PUMPING, LLC 0.03% $11,866.01
A-CORE CONCRETE CUTTING OF TEXAS, INC. 0.03% $11,866.01
FC TRAFFIC CONTROL, INC. 0.00% $0.00
TORO BRAVO CONSTRUCTION, LLC 0.00% $0.00
Total: 10.54% $4,168,924.59

Bid Items & Bid Tabulations

117 Total 0 of 117
ANDREWS  |  SH 115  |  ODESSA  |  0354-06-030  |  08/04/2022  |  $29,597,171.59  |  STP 2022(582)HES  |  CONSTRUCT BRIDGE  |  640 WORKING DAYS
Alt
Item Code
Description
Unit
Quantity
Engineer's Estimate
FNF CONSTRUCTION, INC.
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
PREPARING ROW
AC 60.000 $3,000.000 $5,000.000 $5,500.000
REMOVING STAB BASE AND ASPH PAV (2"-6")
SY 357.000 $9.000 $4.000 $16.000
EXCAVATION (ROADWAY)
CY 94,416.000 $12.000 $11.500 $11.000
EMBANKMENT (FINAL)(DENS CONT)(TY A)
CY 169,129.000 $11.000 $42.000 $9.500
BLADING
HR 100.000 $200.000 $305.000 $400.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 196,522.000 $0.140 $0.250 $0.120
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 196,522.000 $1.000 $0.900 $1.050
PROOF ROLLING
HR 100.000 $130.000 $100.000 $175.000
FL BS (CMP IN PLC)(TY A GR 4) (6")
SY 26,918.000 $14.000 $12.000 $10.750
FL BS (CMP IN PLC)(TY A GR 4)(10")
SY 91,682.000 $17.000 $17.000 $12.500
REWORK BS MTL (TY D)(SURF)(ORD COMP)
SY 199.000 $1.500 $20.000 $25.000
PRIME COAT (AE-P)
GAL 28,551.000 $4.500 $4.750 $4.750
FOG SEAL (CSS-1H)
GAL 493.000 $3.000 $9.000 $14.500
ASPH (AC-20-5TR)
GAL 54,192.000 $6.000 $5.000 $5.320
AGGR(TY-PB GR-4 SAC-A)
CY 1,318.000 $140.000 $160.000 $180.000
CEM STABIL BKFL
CY 551.000 $180.000 $240.000 $330.000
DRILL SHAFT (42 IN)
LF 936.000 $600.000 $675.000 $487.300
DRILL SHAFT (SIGN MTS) (12 IN)
LF 16.000 $260.000 $125.000 $128.700
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 370.000 $270.000 $340.000 $434.500
CL C CONC (ABUT)
CY 118.600 $1,350.000 $2,827.000 $1,540.000
REINF CONC SLAB (HPC)
SF 8,400.000 $30.000 $40.500 $30.800
APPROACH SLAB (HPC)
CY 88.000 $900.000 $1,399.000 $880.000
RETAINING WALL (MSE)
SF 100,866.000 $45.000 $42.500 $100.000
PRESTR CONC GIRDER (TX70)
LF 1,196.000 $350.000 $384.000 $380.600
EPOXY WATERPROOF FINISH (TY X)
SF 3,124.000 $10.000 $10.000 $7.430
RIPRAP (CONC)(4 IN)
CY 774.000 $600.000 $740.000 $627.000
RIPRAP (CONC)(5 IN)
CY 139.000 $465.000 $842.000 $825.000
RIPRAP (CONC)(FLUME)
CY 432.000 $900.000 $800.000 $797.500
RIPRAP (MOW STRIP)(4 IN)
CY 204.000 $450.000 $825.000 $770.000
RAIL (TY SSTR)(HPC)
LF 300.000 $100.000 $160.000 $137.500
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 112.000 $125.000 $400.000 $287.100
CONC BOX CULV (3 FT X 2 FT)
LF 200.000 $195.000 $720.000 $423.500
CONC BOX CULV (5 FT X 3 FT)
LF 267.000 $430.000 $968.000 $715.000
CONC BOX CULV (6 FT X 3 FT)
LF 234.000 $360.000 $942.000 $907.500
RC PIPE (CL III)(18 IN)
LF 1,105.000 $65.000 $135.000 $101.200
MANH (COMPL)(PRM)(48IN)
EA 1.000 $3,800.000 $10,000.000 $6,050.000
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
EA 7.000 $5,000.000 $5,700.000 $7,150.000
SET (TY I)(S=3 FT)(HW=3FT)(4:1)(C)
EA 4.000 $8,000.000 $4,000.000 $5,500.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(4:1) (C)
EA 6.000 $8,000.000 $7,800.000 $8,250.000
SET (TY I)(S= 6 FT)(HW= 4 FT)(4:1) (C)
EA 4.000 $8,000.000 $7,700.000 $9,350.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 4.000 $2,300.000 $1,615.000 $2,750.000
SET (TY II) (24 IN) (RCP) (4: 1) (P)
EA 8.000 $1,800.000 $1,967.000 $3,300.000
MOBILIZATION
LS 1.000 $2,631,651.960 $3,649,000.000 $3,000,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 32.000 $14,000.000 $23,000.000 $15,000.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 1,180.000 $8.000 $9.000 $12.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,180.000 $1.750 $1.750 $6.000
CONSTRUCTING DETOURS
SY 38,224.000 $65.000 $68.000 $77.250
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 6,680.000 $100.000 $134.000 $100.760
RUMBLE STRIPS (SHOULDER)
LF 12,370.000 $0.250 $0.350 $0.220
RUMBLE STRIPS (CENTERLINE)
LF 17,200.000 $0.200 $0.300 $0.240
CONC DIRECTIONAL ISLAND
SY 3,838.000 $93.000 $65.000 $137.500
MTL W-BEAM GD FEN (STEEL POST)
LF 4,700.000 $35.000 $35.000 $39.600
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,800.000 $2,750.000 $3,135.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,230.000 $2,250.000 $1,925.000
MTL BM GD FEN TRANS (NON - SYM)
EA 2.000 $700.000 $1,500.000 $1,595.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,100.000 $3,750.000 $4,070.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 2.000 $30,000.000 $30,000.000 $38,500.000
REMOVE RD IL ASM (TRANS-BASE)
EA 8.000 $1,000.000 $1,700.000 $330.000
IN RD IL (U/P) (TY 2) (150W EQ) LED
EA 4.000 $1,100.000 $3,000.000 $2,200.000
IN RD IL (TY SA) 50T-10 (400W EQ) LED
EA 37.000 $4,200.000 $7,000.000 $8,800.000
CONDT (PVC) (SCH 40) (2")
LF 14,512.000 $26.000 $6.000 $14.300
CONDT (PVC) (SCH 40) (2") (BORE)
LF 543.000 $22.000 $52.000 $46.200
CONDT (RM) (1")
LF 459.000 $20.000 $51.000 $49.500
ELEC CONDR (NO.10) BARE
LF 459.000 $1.200 $2.300 $2.200
ELEC CONDR (NO.10) INSULATED
LF 459.000 $1.300 $3.000 $2.480
ELEC CONDR (NO.6) BARE
LF 15,815.000 $1.500 $3.000 $3.300
ELEC CONDR (NO.6) INSULATED
LF 15,815.000 $1.500 $4.000 $3.580
GROUND BOX TY A (122311)W/APRON
EA 34.000 $1,100.000 $1,650.000 $2,200.000
REMOVE GROUND BOX
EA 21.000 $200.000 $800.000 $330.000
ELC SRV TY A 240/480 060(NS)SS(E)SP(O)
EA 1.000 $6,000.000 $10,000.000 $13,750.000
ALUMINUM SIGNS (TY G)
SF 60.000 $25.000 $45.000 $40.700
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 30.000 $610.000 $1,110.000 $977.900
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 23.000 $690.000 $1,200.000 $1,115.400
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 18.000 $800.000 $1,700.000 $1,554.300
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 12.000 $950.000 $1,800.000 $1,689.600
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
EA 4.000 $1,000.000 $1,745.000 $1,672.000
REMOVE SM RD SN SUP&AM
EA 47.000 $100.000 $160.000 $200.000
INSTALL LRSS (STRUCT STEEL)
LB 390.000 $5.000 $10.000 $9.320
REMOVE DELIN & OBJECT MARKER ASSMS
EA 48.000 $25.000 $35.000 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 54.000 $25.000 $30.000 $49.500
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 65.000 $25.000 $30.000 $49.500
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
EA 48.000 $95.000 $100.000 $92.400
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 16.000 $75.000 $105.000 $96.800
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 228,000.000 $0.200 $0.150 $0.140
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 114,000.000 $0.150 $0.150 $0.150
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 228,000.000 $0.200 $0.150 $0.140
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 11,400.000 $1.300 $0.500 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 11,400.000 $1.000 $0.500 $2.000
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 140.000 $1.000 $1.800 $1.650
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 4,866.000 $0.900 $1.200 $1.060
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 300.000 $3.000 $4.750 $4.400
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 20,320.000 $5.000 $5.500 $5.500
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 1,596.000 $0.400 $1.000 $0.940
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 41,568.000 $0.500 $0.650 $0.650
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 44,878.000 $0.500 $0.650 $0.650
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 48.000 $13.000 $22.000 $22.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 10.000 $210.000 $375.000 $352.000
PREFAB PAV MRK TY C (W) (WORD)
EA 18.000 $250.000 $450.000 $440.000
REFL PAV MRKR TY I-C
EA 949.000 $3.500 $5.000 $4.400
REFL PAV MRKR TY II-A-A
EA 346.000 $3.000 $5.000 $4.400
REFL PAV MRKR TY II-C-R
EA 270.000 $3.000 $5.000 $4.400
ELIM EXT PAV MRK & MRKS (4")
LF 152,000.000 $0.500 $0.500 $0.500
PAV SURF PREP FOR MRK (4")
LF 760.000 $0.750 $0.400 $0.390
REMOV RDSD FLSH BCN AM (SOLAR PWRD)
EA 6.000 $900.000 $750.000 $605.000
REMOVAL OF CABLES
LF 3,016.000 $0.600 $3.500 $0.550
ANTI - GRAFFITI COATNG(PERMNENT-TY III)
SF 100,866.000 $0.900 $0.950 $0.860
D-GR HMA TY-D SAC-B PG64-22
TON 40.000 $150.000 $300.000 $700.000
SP MIXES SP-B SAC-B PG70-22
TON 49,518.000 $115.000 $100.000 $135.000
TACK COAT
GAL 11,411.000 $3.250 $6.000 $3.740
STONE-MTRX-ASPH SMAR-F SAC-A
TON 11,766.000 $150.000 $150.000 $192.000
BONDING COURSE
GAL 11,437.000 $3.500 $5.000 $4.440
THERMO PIPE(24")(PP)(TY S)(TY II)
LF 124.000 $75.000 $107.000 $88.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $13,600.000 $19,250.000
TMSP RADAR SPEED CONTROL MONITOR
EA 4.000 $9,000.000 $13,600.000 $16,500.000
TMA (STATIONARY)
DAY 580.000 $125.000 $196.000 $110.000
TMA (MOBILE OPERATION)
HR 540.000 $65.000 $65.000 $93.500
1
RC PIPE (CL III)(24 IN)
LF 124.000 $75.000 $0.000 $0.000
Totals: $29,606,471.590 $36,740,466.750 $37,953,958.850