ANDERSON US0175 (6378-11-001)

Items: 7

County: ANDERSON
Length: N/A
Highway: US0175
District: TYLER
Control Number: 6378-11-001
DBE Goal: N/A
Project: MMC - 637811001
Guaranty: N/A
Time: 120 CALENDAR DAYS
Engineer's Estimate: $172,000.00
Date: 04/13/2021 (5 years ago)
Contract Number: N/A
Type: ROCK/RIPRAP
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (3)
E
Engineer's Estimate
$172,000.00
$101,515.50
Over/Under Est: -40.98% -$70,484.50
Over/Under Est: -1.6% -$2,750.00
Amt Left: 66.72% $67,734.50
Over/Under Est: 20.17% $34,700.00
Amt Left: 103.61% $105,184.50
Delta: -22.13% -$37,450.00

Bid Items & Bid Tabulations

7 Total 0 of 7
ANDERSON  |  US0175  |  TYLER  |  6378-11-001  |  04/13/2021  |  $172,000.00  |  MMC - 637811001  |  ROCK/RIPRAP  |  120 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
A. L. HELMCAMP, INC.
DIGG COMMERCIAL, LLC
TOUCHSTONE RESOURCES, LLC
RIPRAP (STN CMN)(DRY)(18IN)(VEH)(ST 1)
CY 300.000 $150.000 $55.680 $99.000 $118.000
RIPRAP (STN CMN)(DRY)(18IN)(VEH)(ST 2)
CY 150.000 $150.000 $53.550 $99.000 $118.000
RIPRAP (DEL)(STONE PROT)(18 IN)(SITE 1)
CY 300.000 $100.000 $61.280 $99.000 $118.000
RIPRAP (DEL)(STONE PROT)(18 IN)(SITE 2)
CY 150.000 $100.000 $59.150 $99.000 $118.000
RIPRAP(STN TY R)(DRY)(12 IN)(VEH)(DEL)
CY 200.000 $70.000 $59.150 $89.000 $119.000
RIPRAP(STN TY R)(DRY)(18 IN)(VEH)(DEL)
CY 500.000 $70.000 $58.480 $95.000 $118.000
RIPRAP(DEL)(STONE PROT)(24 IN)(SITE 2)
CY 150.000 $70.000 $56.350 $99.000 $118.000
Totals: $172,000.000 $101,515.500 $169,250.000 $206,700.000