ANDERSON US 79 (0205-07-080)
Items: 22
County: ANDERSON
Length: N/A
Highway: US 79
District: TYLER
Control Number: 0205-07-080
DBE Goal: N/A
Project: F 2024(025)
Guaranty: N/A
Time: 18 WORKING DAYS
Engineer's Estimate: $495,350.40
Date: 09/07/2023 (2 years ago)
Contract Number: N/A
Type: RESURFACE ROADWAY
Mail/Deliver Bids To: N/A
DANNY HENDERSON
LOUIS MCDOW
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$495,350.40 | |||
| $664,721.00 |
34.19%
$169,370.60
|
|||
| $750,490.00 |
51.51%
$255,139.60
|
12.9%
$85,769.00
|
||
| $986,316.00 |
99.11%
$490,965.60
|
48.38%
$321,595.00
|
-31.42%
-$235,826.00
|
E
Engineer's Estimate
$495,350.40
1
Awarded
$664,721.00
Over/Under Est:
34.19%
$169,370.60
$750,490.00
Over/Under Est:
51.51%
$255,139.60
Amt Left:
12.9%
$85,769.00
$986,316.00
Over/Under Est:
99.11%
$490,965.60
Amt Left:
48.38%
$321,595.00
Delta:
-31.42%
-$235,826.00
| Subcontractor | Percentage | Amount |
|---|---|---|
| STRIPING TECHNOLOGY, L.P. | 9.54% | $73,252.41 |
| FLEX SUPPLY, LLC | 0.41% | $3,148.16 |
| Total: | 9.95% | $76,400.57 |
Bid Items & Bid Tabulations
22
Total
0 of 22