Job Info for 0109-02-026

County: ANDERSON Highway: US 287 Date: 05/02/2018 (6 years ago) Engineer's Estimate: $4,111,723 Control Number: 0109-02-026
Project: STP 2018(809) District: TYLER Time: 73 WORKING DAYS Type: PLNG,ACP,OCST,PFC,PVT MRKG

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $4,111,722.55
BIG CREEK CONSTRUCTION, LTD.   $3,987,345.30 1
-3.02% | -$124,377.25
LONGVIEW BRIDGE AND ROAD, LTD.   $4,515,423.15 2
9.82% | $403,700.60
13.24% | $528,077.85
OLDCASTLE MATERIALS TEXAS, INC.   $4,565,107.51 3
11.03% | $453,384.96
14.49% | $577,762.21
1.10% | $49,684.36
A. L. HELMCAMP, INC.   $4,607,866.09 4
12.07% | $496,143.54
15.56% | $620,520.79
0.94% | $42,758.58
EAST TEXAS BRIDGE, INC.   $4,705,154.75 5
14.43% | $593,432.20
18% | $717,809.45
2.11% | $97,288.66

Bid Items

Items: 44, 0 filtered
ANDERSON US 287  |  TYLER  |  0109-02-026  |  05/02/2018  |  $4,111,723  |  STP 2018(809)  |  PLNG,ACP,OCST,PFC,PVT MRKG  |  73 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate BIG CREEK CONSTRUCTION, LTD. LONGVIEW BRIDGE AND ROAD, LTD. OLDCASTLE MATERIALS TEXAS, INC. A. L. HELMCAMP, INC. EAST TEXAS BRIDGE, INC.
132 6021 EMBANKMENT (VEHICLE)(ORD COMP)(TY C) CY 106.000 $30.000 $50.000 $34.000 $50.000 $50.000 $40.000
134 6002 BACKFILL (TY B) STA 87.420 $240.000 $150.000 $200.000 $165.000 $165.000 $400.000
164 6009 BROADCAST SEED (TEMP) (WARM) SY 451.000 $0.150 $1.500 $1.400 $1.250 $2.000 $1.000
164 6011 BROADCAST SEED (TEMP) (COOL) SY 451.000 $0.150 $1.500 $1.400 $1.250 $2.000 $1.000
164 6054 BOND FBR MTRX SEED (PERM)(RURAL)(SAND) SY 899.000 $1.200 $2.500 $2.200 $2.000 $5.000 $3.000
168 6001 VEGETATIVE WATERING MG 20.000 $20.000 $50.000 $25.000 $45.000 $39.000 $15.000
316 6406 ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR) GAL 56,021.000 $2.750 $3.000 $2.750 $3.509 $3.000 $3.500
316 6407 AGGR (TY-PD GR-3 OR TY-PL GR-3) CY 1,270.000 $110.000 $117.000 $118.000 $128.641 $108.000 $145.000
342 6002 PFC (ASPHALT) PG76-22 TON 433.000 $120.000 $125.000 $140.000 $142.000 $148.000 $135.000
342 6006 PFC-C (AGGREGATE)(PG76 MIX) SAC-A TON 6,788.000 $120.000 $125.000 $140.000 $142.000 $148.000 $135.000
344 6050 SUPERPAVE MIXTURES SP-C PG70-22 TON 21,670.000 $87.000 $90.000 $95.000 $100.000 $104.000 $100.000
351 6019 FLEXIBLE PAVEMENT STRUCTURE REPAIR(3") SY 5,555.000 $27.000 $22.000 $34.000 $27.000 $24.000 $30.000
354 6051 PLANE ASPH CONC PAV (0" TO 1 1/2") SY 1,466.000 $2.500 $4.000 $10.000 $3.100 $2.500 $4.000
354 6100 PLANE ASPH CONC PAV (5") SY 78,799.000 $3.000 $3.000 $3.000 $3.100 $3.300 $4.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 66.000 $525.000 $650.000 $520.000 $485.000 $600.000 $450.000
500 6001 MOBILIZATION LS 1.000 $413,000.000 $187,500.000 $440,000.000 $320,705.000 $327,000.000 $350,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $5,000.000 $5,000.000 $2,200.000 $14,000.000 $6,100.000 $10,000.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,030.000 $3.100 $3.000 $3.250 $2.950 $4.000 $3.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,030.000 $1.000 $0.650 $1.100 $1.000 $1.000 $1.000
533 6001 RUMBLE STRIPS (SHOULDER) LF 51,400.000 $0.200 $0.200 $0.160 $0.090 $0.170 $0.250
533 6002 RUMBLE STRIPS (CENTERLINE) LF 25,175.000 $0.300 $0.200 $0.180 $0.140 $0.170 $0.250
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 550.000 $20.000 $30.000 $21.000 $22.000 $20.000 $22.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 350.000 $3.000 $3.000 $5.500 $4.100 $3.000 $4.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 8.000 $2,260.000 $2,300.000 $2,775.000 $2,450.000 $2,400.000 $2,500.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 8.000 $650.000 $250.000 $440.000 $375.000 $260.000 $250.000
658 6061 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 EA 23.000 $28.000 $25.000 $41.000 $38.000 $25.000 $30.000
662 6001 WK ZN PAV MRK NON-REMOV (W)4"(BRK) LF 2,440.000 $0.250 $0.150 $0.160 $0.150 $0.160 $0.200
662 6004 WK ZN PAV MRK NON-REMOV (W)4"(SLD) LF 108,800.000 $0.250 $0.150 $0.130 $0.120 $0.130 $0.150
662 6032 WK ZN PAV MRK NON-REMOV (Y)4"(BRK) LF 10,600.000 $0.250 $0.150 $0.160 $0.150 $0.160 $0.200
662 6034 WK ZN PAV MRK NON-REMOV (Y)4"(SLD) LF 51,860.000 $0.200 $0.150 $0.130 $0.120 $0.130 $0.150
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 366.000 $1.000 $1.000 $1.200 $1.000 $1.500 $2.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 2,884.000 $0.650 $1.000 $1.200 $1.000 $1.500 $2.000
662 6112 WK ZN PAV MRK SHT TERM RMV (W)(4") LF 1,098.000 $0.750 $0.500 $1.400 $1.100 $0.500 $2.000
662 6113 WK ZN PAV MRK SHT TERM RMV (Y)(4") LF 16,436.000 $1.000 $0.500 $1.400 $1.200 $0.500 $2.000
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 197.000 $5.400 $6.000 $5.850 $5.300 $5.570 $6.000
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 1,220.000 $0.350 $0.460 $0.500 $0.460 $0.480 $0.500
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 54,400.000 $0.350 $0.400 $0.440 $0.400 $0.420 $0.450
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 5,300.000 $0.350 $0.460 $0.500 $0.460 $0.480 $0.500
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 25,930.000 $0.350 $0.420 $0.460 $0.580 $0.440 $0.450
672 6007 REFL PAV MRKR TY I-C EA 61.000 $4.000 $3.300 $3.650 $3.300 $3.470 $4.000
672 6009 REFL PAV MRKR TY II-A-A EA 3,054.000 $4.000 $3.300 $3.650 $3.300 $3.470 $4.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 14.000 $100.000 $150.000 $100.000 $100.000 $275.000 $200.000
6185 6001 TMA (STATIONARY) EA 1.000 $8,000.000 $15,000.000 $24,000.000 $14,755.120 $10,000.000 $30,000.000
6185 6002 TMA (STATIONARY) DAY 30.000 $200.000 $500.000 $200.000 $192.698 $250.000 $300.000
Totals: $4,111,722.55 $3,987,345.30 $4,515,423.15 $4,565,107.52 $4,607,866.09 $4,705,154.75