ANDERSON US 287 (0109-01-062)

Items: 124

County: ANDERSON
Length: N/A
Highway: US 287
District: TYLER
Control Number: 0109-01-062
DBE Goal: N/A
Project: STP 2019(092)
Guaranty: N/A
Time: 195 WORKING DAYS
Engineer's Estimate: $6,226,272.25
Date: 10/03/2018 (7 years ago)
Contract Number: N/A
Type: BS RPR,TRT SBGD,ACP,OCST,PFC,STRS,SIGNS,PM
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$6,226,272.25
$6,180,316.71
Over/Under Est: -0.74% -$45,955.54
Over/Under Est: 7.48% $465,838.50
Amt Left: 8.28% $511,794.04
Over/Under Est: 13.42% $835,821.91
Amt Left: 14.27% $881,777.45
Delta: -5.53% -$369,983.41
Over/Under Est: 14.45% $899,639.58
Amt Left: 15.3% $945,595.12
Delta: -0.90% -$63,817.67
Over/Under Est: 30.8% $1,917,660.84
Amt Left: 31.77% $1,963,616.38
Delta: -14.29% -$1,018,021.26

Bid Items & Bid Tabulations

124 Total 0 of 124
ANDERSON  |  US 287  |  TYLER  |  0109-01-062  |  10/03/2018  |  $6,226,272.25  |  STP 2019(092)  |  BS RPR,TRT SBGD,ACP,OCST,PFC,STRS,SI...  |  195 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
A. L. HELMCAMP, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
EAST TEXAS BRIDGE, INC.
DREWERY CONSTRUCTION COMPANY, INCORPORATED
L. S. EQUIPMENT CO., INC.
PREPARING ROW
STA 5.600 $950.000 $4,000.000 $2,500.000 $7,000.000 $15,000.000 $5,000.000
REMOVING CONC (DRIVEWAYS)
SY 461.000 $14.000 $25.000 $22.000 $30.000 $30.000 $10.000
REMOVING CONC (CURB)
LF 450.000 $12.000 $11.000 $12.000 $5.000 $10.000 $17.000
EXCAVATION (ROADWAY)
CY 7,466.000 $9.000 $9.000 $8.000 $10.000 $9.000 $15.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 21,914.000 $12.500 $13.000 $9.000 $15.000 $25.000 $25.000
BACKFILL (TY A)
STA 95.250 $250.000 $270.000 $280.000 $400.000 $350.000 $325.000
BACKFILL (TY B)
STA 11.000 $175.000 $150.000 $375.000 $400.000 $600.000 $325.000
FURNISHING AND PLACING TOPSOIL (4")
SY 95,129.000 $2.500 $0.400 $1.000 $1.250 $1.250 $1.500
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 95,129.000 $1.000 $0.700 $0.750 $0.900 $0.750 $1.000
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 47,569.000 $0.850 $0.700 $0.750 $0.800 $0.720 $1.000
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 47,569.000 $0.850 $0.700 $0.750 $0.800 $0.700 $1.000
VEGETATIVE WATERING
MG 1,046.000 $10.000 $24.000 $2.000 $12.000 $10.000 $1.000
LIME (HYDRATED LIME (DRY))
TON 237.000 $180.000 $160.000 $220.000 $200.000 $170.000 $165.000
LIME TRT (EXST MATL)(8")
SY 11,433.000 $3.500 $2.500 $2.250 $3.000 $7.000 $3.750
CEMENT
TON 237.000 $142.000 $150.000 $190.000 $155.000 $135.000 $155.000
CEMENT TREAT (SUBGRADE) (8")
SY 11,433.000 $6.000 $3.500 $2.250 $2.500 $6.000 $3.750
EMULS ASPH (EROSN CONT)(CSS-1)
GAL 2,870.000 $5.000 $3.800 $4.500 $5.000 $3.000 $5.000
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 55,462.000 $2.700 $3.500 $3.300 $4.250 $3.000 $4.000
AGGR (TY-PD GR-3 OR TY-PL GR-3)
CY 1,321.000 $127.000 $120.000 $125.000 $135.000 $115.000 $125.000
D-GR HMA(SQ) TY-D PG64-22
TON 28.000 $130.000 $175.000 $240.000 $300.000 $150.000 $150.000
PFC (ASPHALT) PG76-22
TON 570.000 $120.000 $119.000 $165.000 $155.000 $1.000 $135.000
PFC-C (AGGREGATE)(PG76 MIX) SAC-A
TON 8,929.000 $105.000 $119.000 $165.000 $155.000 $148.000 $142.000
SUPERPAVE MIXTURES SP-B PG64-22
TON 11,502.000 $90.000 $94.000 $107.000 $105.000 $101.000 $135.000
SUPERPAVE MIXTURES SP-D PG64-22
TON 3,316.000 $95.000 $97.000 $107.000 $110.000 $120.000 $135.000
SUPERPAVE MIXTURES SP-D SAC-A PG70-22
TON 265.000 $97.000 $130.000 $125.000 $150.000 $140.000 $165.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 10,000.000 $45.000 $48.000 $54.000 $50.000 $47.500 $70.000
PLANE CONC PAV(0" TO 1-1/2")
SY 3,117.000 $4.250 $3.000 $2.650 $3.000 $6.250 $3.000
PLANE ASPH CONC PAV (1.5")
SY 21,214.000 $2.800 $2.000 $2.250 $3.000 $4.000 $3.000
FLOWABLE BACKFILL
CY 2.000 $200.000 $800.000 $800.000 $500.000 $675.000 $1,000.000
TEMPORARY SPL SHORING
SF 2,300.000 $21.000 $26.000 $40.000 $45.000 $30.000 $50.000
CL C CONC (COLLAR)
EA 5.000 $715.000 $1,100.000 $1,150.000 $650.000 $1,100.000 $1,000.000
CL E CONC (SEAL SLAB)
CY 4.000 $400.000 $500.000 $600.000 $400.000 $425.000 $500.000
RIPRAP (CONC)(5 IN)
CY 4.000 $500.000 $550.000 $565.000 $600.000 $525.000 $1,000.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 42.000 $130.000 $110.000 $240.000 $200.000 $120.000 $200.000
RIPRAP (MOW STRIP)(4 IN)
CY 38.000 $480.000 $550.000 $535.000 $450.000 $525.000 $400.000
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 200.000 $20.000 $64.000 $45.000 $65.000 $75.000 $70.000
RETROFIT RAIL (TY T223)
LF 212.000 $150.000 $200.000 $165.000 $250.000 $125.000 $125.000
CONC BOX CULV (8 FT X 6 FT)(EXTEND)
LF 8.000 $650.000 $740.000 $1,025.000 $1,000.000 $750.000 $500.000
CONC BOX CULV (8 FT X 10 FT) (EXTEND)
LF 15.000 $1,750.000 $1,000.000 $1,200.000 $1,000.000 $1,000.000 $500.000
CONC BOX CULVERT (4 FT X 5 FT)(EXTEND)
LF 6.000 $550.000 $480.000 $1,120.000 $700.000 $500.000 $300.000
RC PIPE (CL III)(18 IN)
LF 744.000 $48.000 $44.000 $40.000 $40.000 $45.000 $35.000
RC PIPE (CL III)(24 IN)
LF 458.000 $69.000 $84.000 $70.000 $55.000 $85.000 $55.000
RC PIPE (CL III)(30 IN)
LF 30.000 $86.000 $160.000 $115.000 $80.000 $160.000 $100.000
HEADWALL (CH - PW - 0) (DIA= 24 IN)
EA 2.000 $3,500.000 $3,700.000 $4,000.000 $4,000.000 $3,700.000 $3,500.000
WINGWALL (FW - 0) (HW=6 FT)
EA 1.000 $8,400.000 $7,400.000 $14,000.000 $8,000.000 $7,400.000 $5,000.000
WINGWALL (PW - 2) (HW=11 FT)
EA 1.000 $45,000.000 $51,000.000 $48,000.000 $45,000.000 $40,000.000 $25,000.000
WINGWALL (PW - 2) (HW=15 FT)
EA 1.000 $60,000.000 $92,000.000 $75,000.000 $90,000.000 $60,000.000 $45,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 63.000 $655.000 $740.000 $625.000 $560.000 $750.000 $800.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 2.000 $975.000 $780.000 $930.000 $600.000 $800.000 $900.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 4.000 $800.000 $850.000 $1,030.000 $700.000 $850.000 $800.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 28.000 $1,000.000 $900.000 $825.000 $900.000 $900.000 $950.000
SET (TY II) (30 IN) (RCP) (3: 1) (C)
EA 1.000 $890.000 $2,200.000 $1,200.000 $900.000 $2,100.000 $1,900.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 1.000 $1,300.000 $2,500.000 $1,375.000 $1,100.000 $2,500.000 $1,900.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 2.000 $2,000.000 $3,000.000 $1,650.000 $1,600.000 $2,950.000 $2,500.000
CLEAN EXIST CULVERTS
EA 5.000 $1,500.000 $1,300.000 $3,000.000 $1,000.000 $1,300.000 $1,000.000
REMOV STR (PIPE)
EA 45.000 $378.000 $470.000 $285.000 $500.000 $455.000 $1,000.000
MOBILIZATION
LS 1.000 $556,100.000 $520,000.000 $400,000.000 $500,000.000 $700,000.000 $650,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 19.000 $4,800.000 $7,000.000 $1,600.000 $6,000.000 $3,500.000 $4,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 500.000 $22.500 $35.000 $38.500 $40.000 $30.000 $75.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 840.000 $26.000 $36.000 $42.000 $45.000 $40.000 $75.000
ROCK FILTER DAMS (REMOVE)
LF 1,340.000 $4.550 $3.000 $22.000 $20.000 $7.250 $5.000
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
CY 1,000.000 $17.000 $8.000 $11.000 $30.000 $20.000 $50.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 150.000 $83.000 $65.000 $150.000 $125.000 $110.000 $100.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 10,250.000 $2.850 $2.800 $3.100 $3.500 $2.750 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 10,250.000 $0.750 $0.500 $1.650 $1.500 $1.580 $1.000
TRACKHOE WORK (EROSION & SEDMT CONT)
HR 150.000 $150.000 $86.000 $150.000 $200.000 $179.840 $100.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 420.000 $78.000 $80.000 $90.000 $90.000 $100.000 $70.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 420.000 $15.000 $11.000 $12.000 $10.000 $12.000 $50.000
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 420.000 $11.000 $25.000 $14.500 $20.000 $30.000 $50.000
INTERSECTIONS (ACP)
SY 3,348.000 $90.000 $58.000 $52.000 $30.000 $40.000 $70.000
DRIVEWAYS (ACP)
SY 3,618.000 $40.000 $28.000 $34.000 $30.000 $34.000 $70.000
DRIVEWAYS (CONC) (HES)
SY 461.000 $90.000 $125.000 $85.000 $90.000 $125.000 $75.000
RUMBLE STRIPS (SHOULDER)
LF 33,350.000 $0.220 $0.250 $0.200 $0.250 $0.190 $0.140
RUMBLE STRIPS (CENTERLINE)
LF 15,094.000 $0.370 $0.250 $0.200 $0.250 $0.240 $0.160
CONC MEDIAN
SY 88.000 $93.000 $110.000 $110.000 $150.000 $105.000 $125.000
CONC DIRECTIONAL ISLAND
SY 128.000 $82.000 $110.000 $105.000 $150.000 $105.000 $125.000
MTL W-BEAM GD FEN (TIM POST)
LF 550.000 $21.000 $21.000 $22.000 $23.000 $21.000 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,510.000 $1,500.000 $1,500.000 $1,700.000 $1,500.000 $1,600.000
REMOVE METAL BEAM GUARD FENCE
LF 504.000 $3.600 $2.200 $2.750 $3.000 $2.750 $6.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,270.000 $2,700.000 $2,750.000 $3,000.000 $2,625.000 $2,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $265.000 $270.000 $220.000 $300.000 $210.000 $250.000
CRASH CUSH ATTEN (INSTL)
EA 2.000 $10,500.000 $9,000.000 $12,500.000 $12,000.000 $9,700.000 $7,000.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $1,600.000 $1,200.000 $2,750.000 $3,000.000 $2,625.000 $2,000.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $850.000 $750.000 $1,100.000 $1,500.000 $1,050.000 $1,000.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 20.000 $200.000 $220.000 $550.000 $550.000 $220.000 $125.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 2.000 $240.000 $260.000 $575.000 $600.000 $265.000 $250.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $600.000 $550.000 $395.000 $600.000 $550.000 $478.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 63.000 $341.000 $320.000 $350.000 $400.000 $320.000 $475.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 4.000 $328.000 $270.000 $405.000 $300.000 $273.000 $500.000
REMOVE SM RD SN SUP&AM
EA 5.000 $100.000 $80.000 $260.000 $100.000 $80.000 $400.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $34.000 $25.000 $16.500 $30.000 $15.750 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 51.000 $26.000 $30.000 $22.000 $30.000 $21.000 $100.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 2,834.000 $0.140 $0.220 $0.220 $0.220 $0.210 $0.150
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 44,120.000 $0.120 $0.140 $0.140 $0.150 $0.140 $0.150
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 800.000 $0.320 $0.550 $0.550 $0.550 $0.530 $0.300
WK ZN PAV MRK NON-REMOV (W)18"(SLD)
LF 52.000 $2.000 $2.200 $2.200 $2.200 $2.100 $15.000
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 330.000 $2.100 $2.200 $2.200 $2.200 $2.100 $15.000
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 3,734.000 $0.160 $0.220 $0.220 $0.220 $0.210 $0.150
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 44,420.000 $0.160 $0.140 $0.140 $0.150 $0.140 $0.150
WK ZN PAV MRK REMOV (TRAF BTN) TY W
LF 8,000.000 $0.400 $0.700 $0.900 $0.900 $0.840 $3.000
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
LF 8,000.000 $0.400 $0.700 $0.900 $0.900 $0.840 $3.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 934.000 $1.000 $0.600 $1.450 $2.000 $1.000 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,348.000 $1.350 $0.600 $1.450 $2.000 $1.000 $1.000
WK ZN PAV MRK SHT TERM RMV (W)(4")
LF 1,010.000 $1.150 $0.700 $1.650 $2.000 $1.000 $2.000
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 11,159.000 $0.750 $0.700 $1.650 $2.000 $1.000 $2.000
REFL PAV MRK TY I (W)4"(LNDP)(100MIL)
LF 472.000 $1.000 $1.100 $1.100 $1.100 $1.050 $2.500
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 800.000 $0.830 $1.100 $1.100 $1.100 $1.050 $5.000
REFL PAV MRK TY I (W)18"(SLD)(100MIL)
LF 52.000 $2.750 $5.300 $5.500 $5.500 $5.250 $13.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 375.000 $5.250 $6.000 $6.050 $6.000 $5.780 $17.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 2,519.000 $0.380 $0.550 $0.550 $0.550 $0.530 $0.400
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 41,720.000 $0.380 $0.450 $0.440 $0.450 $0.420 $0.400
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 3,734.000 $0.440 $0.550 $0.550 $0.550 $0.530 $0.400
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 45,386.000 $0.390 $0.450 $0.440 $0.450 $0.420 $0.400
PREFAB PAV MRK TY C (W) (ARROW)
EA 5.000 $180.000 $200.000 $200.000 $200.000 $189.000 $250.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 7.000 $265.000 $260.000 $275.000 $300.000 $262.500 $350.000
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 4.000 $350.000 $350.000 $360.000 $400.000 $341.250 $650.000
PREFAB PAV MRK TY C (W) (WORD)
EA 5.000 $220.000 $230.000 $235.000 $300.000 $225.750 $300.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 1.000 $50.000 $110.000 $110.000 $120.000 $105.000 $30.000
REFL PAV MRKR TY I-C
EA 210.000 $3.500 $3.400 $3.500 $4.000 $3.500 $7.000
REFL PAV MRKR TY II-A-A
EA 1,722.000 $3.500 $3.400 $3.550 $4.000 $3.500 $7.000
ELIM EXT PAV MRK & MRKS (4")
LF 2,400.000 $0.500 $1.000 $0.550 $0.550 $0.550 $0.300
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $9,000.000 $10,000.000 $18,000.000 $20,000.000 $18,500.000 $100.000
TMA (STATIONARY)
EA 1.000 $6,500.000 $20,000.000 $20,000.000 $30,000.000 $7,500.000 $14,000.000
TMA (MOBILE OPERATION)
DAY 40.000 $260.000 $100.000 $27.500 $300.000 $30.000 $35.000
Totals: $6,226,272.250 $6,180,316.710 $6,692,110.750 $7,062,094.160 $7,125,911.830 $8,143,933.090