6391-80-001 |
BEXAR |
SAN ANTONIO |
$268,000 |
IH0035 |
MMC - 639180001 |
11/23/2021 |
11/15/2023 |
HOT-MIX COLD-LAID |
TEXAS MATERIALS GROUP, INC.($298,000) |
|
6391-81-001 |
BEXAR |
SAN ANTONIO |
$244,500 |
IH0035 |
MMC - 639181001 |
11/23/2021 |
11/15/2023 |
HYDRAULIC CEMENT |
TOUCHSTONE RESOURCES, LLC($136,500) |
|
6393-89-001 |
KERR |
SAN ANTONIO |
$282,750 |
IH0010 |
MMC - 639389001 |
11/23/2021 |
11/15/2023 |
LIMESTONE ROCK AND ASPH |
VULCAN CONSTRUCTION MATERIALS, LLC($353,693) |
|
6393-88-001 |
MEDINA |
SAN ANTONIO |
$280,750 |
IH0035 |
MMC - 639388001 |
11/23/2021 |
11/15/2023 |
DENSE GRADED HOT MIX |
TEXAS MATERIALS GROUP, INC.($300,700) |
|
6391-85-001 |
BEXAR |
SAN ANTONIO |
$238,000 |
IH0035 |
MMC - 639185001 |
11/23/2021 |
11/15/2023 |
ROCK/RIPRAP |
DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC.($302,800) |
|
6391-77-001 |
WILSON |
SAN ANTONIO |
$289,000 |
US0181 |
MMC - 639177001 |
11/22/2021 |
11/15/2023 |
LIMESTONE ROCK AND ASPH |
VULCAN CONSTRUCTION MATERIALS, LLC($340,160) |
|
6391-76-001 |
BANDERA |
SAN ANTONIO |
$287,750 |
SH0016 |
MMC - 639176001 |
11/22/2021 |
11/15/2023 |
LIMESTONE ROCK AND ASPH |
VULCAN CONSTRUCTION MATERIALS, LLC($333,735) |
|
6391-72-001 |
COMAL |
SAN ANTONIO |
$264,950 |
IH0035 |
MMC - 639172001 |
11/22/2021 |
11/15/2023 |
EMULSION |
ERGON ASPHALT & EMULSIONS, INC.($270,840) |
|
6391-78-001 |
FRIO |
SAN ANTONIO |
$282,750 |
IH0035 |
MMC - 639178001 |
11/22/2021 |
11/15/2023 |
LIMESTONE ROCK AND ASPH |
VULCAN CONSTRUCTION MATERIALS, LLC($325,363) |
|
6391-71-001 |
KERR |
SAN ANTONIO |
$272,500 |
IH0010 |
MMC - 639171001 |
11/22/2021 |
11/15/2023 |
EMULSION |
ERGON ASPHALT & EMULSIONS, INC.($288,950) |
|
6391-70-001 |
MEDINA |
SAN ANTONIO |
$255,810 |
US0090 |
MMC - 639170001 |
11/22/2021 |
11/15/2023 |
EMULSION |
ERGON ASPHALT & EMULSIONS, INC.($258,900) |
|
0025-03-097 |
GUADALUPE |
SAN ANTONIO |
$140,726,612 |
IH 10 |
F 2022(097) |
11/03/2021 |
11/15/2023 |
WIDEN ROAD - ADD LANES |
WEBBER, LLC($125,021,001) |
|
6378-04-001 |
BEXAR |
SAN ANTONIO |
$232,000 |
IH0010 |
MMC - 637804001 |
10/20/2021 |
11/15/2023 |
WINTER WEATHER MATERIALS |
VULCAN CONSTRUCTION MATERIALS, LLC($66,474) |
|
6391-06-001 |
COMAL |
SAN ANTONIO |
$276,650 |
IH0035 |
MMC - 639106001 |
10/20/2021 |
11/15/2023 |
ENSE GRADED HOT MIX |
COLORADO MATERIALS, LTD.($314,245) |
|
6391-05-001 |
BEXAR |
SAN ANTONIO |
$283,250 |
IH0010 |
MMC - 639105001 |
10/20/2021 |
11/15/2023 |
DENSE GRADED HOT MIX |
TEXAS MATERIALS GROUP, INC.($261,800) |
|
6391-07-001 |
COMAL |
SAN ANTONIO |
$274,550 |
IH0035 |
MMC - 639107001 |
10/20/2021 |
11/15/2023 |
DENSE GRADED HOT MIX |
LONE STAR PAVING COMPANY($323,850) |
|
6391-04-001 |
BEXAR |
SAN ANTONIO |
$283,250 |
IH0010 |
MMC - 639104001 |
10/20/2021 |
11/15/2023 |
DENSE GRADED HOT MIX |
TEXAS MATERIALS GROUP, INC.($261,800) |
|
6378-03-001 |
BEXAR |
SAN ANTONIO |
$178,650 |
IH0010 |
MMC - 637803001 |
10/20/2021 |
11/15/2023 |
WINTER WEATHER MATERIALS |
SOUTHWEST ENVIROTX PARTNERS, LLC($153,654) |
|
6378-02-001 |
BEXAR |
SAN ANTONIO |
$284,000 |
IH0010 |
MMC - 637802001 |
10/20/2021 |
11/15/2023 |
WINTER WEATHER MATERIAL |
TOUCHSTONE RESOURCES, LLC($250,300) |
|
6385-42-001 |
KERR |
SAN ANTONIO |
$1,035,827 |
SL0534 |
RMC - 638542001 |
10/08/2021 |
11/15/2023 |
SPOT BASE REPAIR |
TEXAS MATERIALS GROUP, INC.($1,092,062) |
|
6389-74-001 |
MEDINA |
SAN ANTONIO |
$986,320 |
IH0035 |
RMC - 638974001 |
10/08/2021 |
11/15/2023 |
DEBRIS RMVL |
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.($629,780) |
|
0915-15-097 |
KERR |
SAN ANTONIO |
$675,946 |
CR |
BR 2021(064) |
10/08/2021 |
11/15/2023 |
BRIDGE REPL |
HILL COUNTRY BRIDGE, INC.($596,018) |
|
6388-78-001 |
GUADALUPE |
SAN ANTONIO |
$1,377,557 |
FM1104 |
RMC - 638878001 |
10/07/2021 |
11/15/2023 |
SEAL COAT |
CLARK CONSTRUCTION OF TEXAS, INC.($1,490,762) |
|
0017-01-026 |
BEXAR |
SAN ANTONIO |
$7,209,574 |
SL 353 |
F 2022(032) |
10/07/2021 |
11/15/2023 |
RESURF ROADWAY |
CLARK CONSTRUCTION OF TEXAS, INC.($6,922,526) |
|
6388-36-001 |
BEXAR |
SAN ANTONIO |
$2,895,554 |
IH0035 |
RMC - 638836001 |
10/07/2021 |
11/15/2023 |
PAVMT MRK |
INTERSTATE BARRICADES & MARKINGS, INC.($3,077,768) |
|
0072-05-090 |
KENDALL |
SAN ANTONIO |
$5,756,438 |
IH 10 |
F 2022(034) |
10/07/2021 |
11/15/2023 |
RESURF ROADWAY |
CLARK CONSTRUCTION OF TEXAS, INC.($5,699,778) |
|
6385-41-001 |
MEDINA |
SAN ANTONIO |
$2,069,565 |
FM0462 |
RMC - 638541001 |
09/02/2021 |
11/15/2023 |
SPOT BASE REPAIR |
CLARK CONSTRUCTION OF TEXAS, INC.($1,820,224) |
|
6385-43-001 |
COMAL |
SAN ANTONIO |
$2,096,725 |
FM3009 |
RMC - 638543001 |
09/02/2021 |
11/15/2023 |
SPOT BASE REPAIR |
CLARK CONSTRUCTION OF TEXAS, INC.($1,943,944) |
|
1122-04-012 |
WILSON |
SAN ANTONIO |
$5,354,351 |
FM 1344 |
SSW 1122-4-12 |
09/01/2021 |
11/15/2023 |
HAZARD ELIM & SAFETY |
HUNTER INDUSTRIES, LTD.($6,200,914) |
|
2975-01-009 |
ATASCOSA |
SAN ANTONIO |
$7,418,473 |
FM 2924 |
F 2022(047) |
09/01/2021 |
11/15/2023 |
REHAB EXIST ROADWAY |
HUNTER INDUSTRIES, LTD.($7,308,203) |
|
6385-40-001 |
BEXAR |
SAN ANTONIO |
$2,088,691 |
IH0010 |
RMC - 638540001 |
09/01/2021 |
11/15/2023 |
SPOT BASE REPAIR |
TEXAS MATERIALS GROUP, INC.($1,998,721) |
|
6387-37-001 |
BEXAR |
SAN ANTONIO |
$1,279,000 |
IH0010 |
RMC - 638737001 |
09/01/2021 |
11/15/2023 |
TRAF CONTROL SERVICES |
BARRICADES UNLIMITED($1,112,250) |
|
0017-04-044 |
ATASCOSA |
SAN ANTONIO |
$5,699,774 |
IH 35 |
F 2022(046) |
09/01/2021 |
11/15/2023 |
REHAB EXIST ROADWAY |
ANDERSON COLUMBIA CO., INC.($6,383,622) |
|
0236-04-029 |
FRIO |
SAN ANTONIO |
$25,996,381 |
FM 117 |
C 236-4-29 |
08/05/2021 |
11/15/2023 |
REHAB AND WIDEN NARROW ROADWAY TO ADD SHOULDERS |
HUNTER INDUSTRIES, LTD.($23,587,273) |
|
0024-07-063 |
BEXAR |
SAN ANTONIO |
$2,508,773 |
US 90 |
F 2021(778) |
08/05/2021 |
11/15/2023 |
INTERS IMPRV |
DAN WILLIAMS COMPANY($2,885,971) |
|
0100-02-068 |
BEXAR |
SAN ANTONIO |
$401,211 |
US 181 |
F 2021(779) |
08/04/2021 |
11/15/2023 |
INSTL FLASH BEACON/SFTY LIGHTING @ INTERS |
E-Z BEL CONSTRUCTION, LLC($411,503) |
|
0915-12-625 |
BEXAR |
SAN ANTONIO |
$1,606,979 |
CS |
STP 2021(676)HES |
08/04/2021 |
11/15/2023 |
HAZARD ELIM & SAFETY |
E-Z BEL CONSTRUCTION, LLC($1,494,380) |
|
6382-98-001 |
KERR |
SAN ANTONIO |
$282,750 |
IH0010 |
MMC - 638298001 |
07/21/2021 |
11/15/2023 |
LIMESTONE ROCK AND ASPH |
MARTIN MARIETTA MATERIALS, INC.($213,205) |
|
6383-05-001 |
WILSON |
SAN ANTONIO |
$282,750 |
US0181 |
MMC - 638305001 |
07/21/2021 |
11/15/2023 |
LIMESTONE ROCK AND ASPH |
MARTIN MARIETTA MATERIALS, INC.($307,088) |
|
6383-02-001 |
BANDERA |
SAN ANTONIO |
$282,750 |
SH0016 |
MMC - 638302001 |
07/21/2021 |
11/15/2023 |
LIMESTONE ROCK AND ASPH |
VULCAN CONSTRUCTION MATERIALS, LLC($286,093) |
|
6383-00-001 |
ATASCOSA |
SAN ANTONIO |
$282,750 |
IH0035 |
MMC - 638300001 |
07/21/2021 |
11/15/2023 |
LIMESTONE ROCK AND ASPH |
VULCAN CONSTRUCTION MATERIALS, LLC($305,260) |
|
6382-99-001 |
FRIO |
SAN ANTONIO |
$282,750 |
IH0035 |
MMC - 638299001 |
07/21/2021 |
11/15/2023 |
LIMESTONE ROCK AND ASPH |
MARTIN MARIETTA MATERIALS, INC.($268,225) |
|
6383-01-001 |
MCMULLEN |
SAN ANTONIO |
$282,750 |
US0059 |
MMC - 638301001 |
07/21/2021 |
11/15/2023 |
LIMESTONE ROCK AND ASPH |
MARTIN MARIETTA MATERIALS, INC.($306,875) |
|
6383-06-001 |
GUADALUPE |
SAN ANTONIO |
$282,750 |
IH0010 |
MMC - 638306001 |
07/21/2021 |
11/15/2023 |
LIMESTONE ROCK AND ASPH |
VULCAN CONSTRUCTION MATERIALS, LLC($322,728) |
|
0143-04-071 |
WILSON |
SAN ANTONIO |
$423,586 |
US 87 |
F 2021(674) |
07/02/2021 |
11/15/2023 |
LANDSCAPE DEVELOPMENT |
ENCINO LANDSCAPE, INC.($370,530) |
|
7774-01-004 |
BEXAR |
SAN ANTONIO |
$22,969,734 |
PA 1502 |
F 2021(678) |
07/02/2021 |
11/15/2023 |
HAZARD ELIM & SAFETY |
JORDAN FOSTER CONSTRUCTION, LLC($19,520,130) |
|
6383-15-001 |
KERR |
SAN ANTONIO |
$619,760 |
IH0010 |
RMC - 638315001 |
07/02/2021 |
11/15/2023 |
PICNIC AREA MAINT |
JCW CONSTRUCTION, LLC($599,880) |
|
0023-05-086 |
UVALDE |
SAN ANTONIO |
$1,051,481 |
US 90 |
STP 2021(672)HES |
07/02/2021 |
11/15/2023 |
HAZARD ELIM & SAFETY |
E-Z BEL CONSTRUCTION, LLC($1,296,838) |
|
0915-14-047 |
WILSON |
SAN ANTONIO |
$661,915 |
CR |
BR 2021(063) |
07/02/2021 |
11/15/2023 |
BRIDGE REPL |
HARPER BROTHERS CONSTRUCTION LLC($577,070) |
|
0915-14-046 |
WILSON |
SAN ANTONIO |
$581,756 |
CR |
BR 2021(062) |
07/02/2021 |
11/15/2023 |
BRIDGE REPL |
TASCOSA BRIDGE CO., LC($522,736) |
|
0142-09-044 |
KENDALL |
SAN ANTONIO |
$3,953,037 |
RM 473 |
STP 2021(673)HES |
07/01/2021 |
11/15/2023 |
HAZARD ELIM & SAFETY |
FARIS INDUSTRIES, INC.($3,777,155) |
|
0915-00-234 |
BEXAR |
SAN ANTONIO |
$1,562,265 |
VA |
C 915-00-234 |
07/01/2021 |
11/15/2023 |
TRAF SIGNAL IMPRVS |
VACA UNDERGROUND UTILITIES INC($1,384,854) |
|
0215-09-035 |
GUADALUPE |
SAN ANTONIO |
$12,891,468 |
FM 725 |
F 2021(675) |
07/01/2021 |
11/15/2023 |
WIDEN ROAD - ADD SHOULDERS |
HUNTER INDUSTRIES, LTD.($10,378,166) |
|
1730-01-043 |
BANDERA |
SAN ANTONIO |
$3,129,991 |
FM 1283 |
STP 2021(677)HES |
07/01/2021 |
11/15/2023 |
HAZARD ELIM & SAFETY |
ANGEL BROTHERS HOLDINGS CORP.($2,946,881) |
|
6382-83-001 |
BEXAR |
SAN ANTONIO |
$319,539 |
IH0010 |
RMC - 638283001 |
07/01/2021 |
11/15/2023 |
TRAF SIGNAL MAINT |
E-Z BEL CONSTRUCTION, LLC($333,003) |
|
6377-99-001 |
MEDINA |
SAN ANTONIO |
$280,750 |
IH0035 |
MMC - 637799001 |
06/16/2021 |
11/15/2023 |
HOT MIX |
CENTURY ASPHALT, LTD.($243,700) |
|
6382-96-001 |
MEDINA |
SAN ANTONIO |
$282,750 |
IH0035 |
MMC - 638296001 |
06/16/2021 |
11/15/2023 |
LIMESTONE ROCK AND ASPH |
MARTIN MARIETTA MATERIALS, INC.($264,953) |
|
6382-97-001 |
COMAL |
SAN ANTONIO |
$282,750 |
IH0035 |
MMC - 638297001 |
06/16/2021 |
11/15/2023 |
LIMESTONE ROCK AND ASPH |
VULCAN CONSTRUCTION MATERIALS, LLC($312,698) |
|
6383-04-001 |
KENDALL |
SAN ANTONIO |
$282,750 |
IH0010 |
MMC - 638304001 |
06/16/2021 |
11/15/2023 |
LIMESTONE ROCK AND ASPH |
MARTIN MARIETTA MATERIALS, INC.($296,688) |
|
6377-97-001 |
KERR |
SAN ANTONIO |
$276,000 |
IH0010 |
MMC - 637797001 |
06/16/2021 |
11/15/2023 |
AGGREGATE |
MARTIN MARIETTA MATERIALS, INC.($220,275) |
|
6373-41-001 |
UVALDE |
SAN ANTONIO |
$221,712 |
US0083 |
BPM - 637341001 |
06/16/2021 |
11/15/2023 |
REPLACE BEARING SEAT PADS |
BLACKSMITH VENTURES LLC($76,800) |
|
6382-84-001 |
BEXAR |
SAN ANTONIO |
$264,510 |
IH0410 |
RMC - 638284001 |
06/16/2021 |
11/15/2023 |
CRACK SEAL |
TALBRAN ENTERPRISES LLC($261,303) |
|
6382-86-001 |
KERR |
SAN ANTONIO |
$164,520 |
US0083 |
RMC - 638286001 |
06/16/2021 |
11/15/2023 |
CRACK SEAL |
TALBRAN ENTERPRISES LLC($186,545) |
|
6382-87-001 |
COMAL |
SAN ANTONIO |
$273,330 |
FM3009 |
RMC - 638287001 |
06/16/2021 |
11/15/2023 |
CRACK SEAL |
TALBRAN ENTERPRISES LLC($288,634) |
|
6383-03-001 |
UVALDE |
SAN ANTONIO |
$282,750 |
US0090 |
MMC - 638303001 |
06/16/2021 |
11/15/2023 |
LIMESTONE ROCK AND ASPH |
MARTIN MARIETTA MATERIALS, INC.($237,413) |
|
6377-98-001 |
MEDINA |
SAN ANTONIO |
$276,000 |
IH0035 |
MMC - 637798001 |
06/16/2021 |
11/15/2023 |
AGGREGATE |
VULCAN CONSTRUCTION MATERIALS, LLC($232,650) |
|
6382-85-001 |
MEDINA |
SAN ANTONIO |
$229,380 |
US0090 |
RMC - 638285001 |
06/16/2021 |
11/15/2023 |
CRACK SEAL |
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY($193,451) |
|
6378-01-001 |
BEXAR |
SAN ANTONIO |
$276,000 |
IH0010 |
MMC - 637801001 |
06/16/2021 |
11/15/2023 |
AGGREGATE |
MARTIN MARIETTA MATERIALS, INC.($207,315) |
|
6377-93-001 |
BEXAR |
SAN ANTONIO |
$282,750 |
IH0010 |
MMC - 637793001 |
06/16/2021 |
11/15/2023 |
LIMESTONE ROCK AND ASPH |
VULCAN CONSTRUCTION MATERIALS, LLC($293,955) |
|
6378-00-001 |
BEXAR |
SAN ANTONIO |
$279,600 |
IH0010 |
MMC - 637800001 |
06/16/2021 |
11/15/2023 |
EMULSION |
ERGON ASPHALT & EMULSIONS, INC.($265,140) |
|
6375-09-001 |
MEDINA |
SAN ANTONIO |
$1,447,446 |
IH0035 |
EMC - 637509001 |
06/09/2021 |
11/15/2023 |
REPLACE DAMAGED BRIDGE GIRDERS |
GIBSON & ASSOCIATES, INC.($1,183,845) |
|
0016-05-120 |
COMAL |
SAN ANTONIO |
$5,591,576 |
IH 35 |
C 16-5-120 |
06/04/2021 |
11/15/2023 |
HWY IMPRV |
ANGEL BROTHERS HOLDINGS CORP.($5,145,675) |
|
1268-01-013 |
COMAL |
SAN ANTONIO |
$40,975,029 |
FM 1103 |
C 1268-1-13 |
06/04/2021 |
11/15/2023 |
EXPAND 2 TO 4 LN W/MEDIANS, TRN LNS, SDWK & BK LNS |
HUNTER INDUSTRIES, LTD.($39,295,624) |
|
0073-02-080 |
BEXAR |
SAN ANTONIO |
$5,066,580 |
US 281 |
C 73-2-80 |
06/04/2021 |
11/15/2023 |
INTERS IMPRVS WITH RIGHT AND/OR LEFT T |
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.($4,316,413) |
|
6379-83-001 |
BEXAR |
SAN ANTONIO |
$2,915,554 |
IH0035 |
RMC - 637983001 |
06/03/2021 |
11/15/2023 |
PAVMT MRK |
PAVEMENT MARKINGS INC.($2,806,412) |
|
2452-02-128 |
BEXAR |
SAN ANTONIO |
$256,245,119 |
SL 1604 |
STP 2021(616)MM |
06/03/2021 |
11/15/2023 |
WIDEN ROAD - ADD LANES |
ZACHRY CONSTRUCTION CORPORATION($243,941,845) |
|
6374-16-001 |
BEXAR |
SAN ANTONIO |
$272,608 |
SL1604 |
BPM - 637416001 |
05/12/2021 |
09/26/2024 |
EROSION CONTROL |
BECK-REIT & SONS, LTD.($206,056) |
|
0511-02-026 |
COMAL |
SAN ANTONIO |
$978,551 |
RM 32 |
BR 2021(548) |
05/06/2021 |
11/15/2023 |
BRIDGE REPL |
SB CONTRACTORS LLC($1,044,625) |
|
0915-00-202 |
BEXAR |
SAN ANTONIO |
$636,414 |
VA |
C 915-00-202 |
05/06/2021 |
11/15/2023 |
PURCHASE AND INSTL SIGNS & EQUIP |
THE LEVY COMPANY, INC.($676,228) |
|
0073-12-015 |
BEXAR |
SAN ANTONIO |
$12,566,158 |
US 181 |
C 73-12-15 |
05/05/2021 |
11/15/2023 |
RESURF ROADWAY |
CLARK CONSTRUCTION OF TEXAS, INC.($8,387,879) |
|
0915-00-200 |
BEXAR |
SAN ANTONIO |
$639,149 |
VA |
C 915-00-200 |
05/05/2021 |
11/15/2023 |
INSTL ADVANCED TRAF MGT SYSTEM |
THIRD COAST SERVICES LLC($477,879) |
|
0915-45-055 |
MEDINA |
SAN ANTONIO |
$442,828 |
CR |
BR 2021(142) |
05/05/2021 |
11/15/2023 |
BRIDGE REPL |
DELGADO'S CONTRACTORS, LLC($419,500) |
|
6359-10-001 |
GUADALUPE |
SAN ANTONIO |
$164,333 |
SH0046 |
TMC - 635910001 |
05/05/2021 |
11/15/2023 |
DELINEATORS SEGUIN RDC (MATERIAL ONLY) |
CENTERLINE SUPPLY, INC.($154,910) |
|
0521-05-148 |
BEXAR |
SAN ANTONIO |
$23,897,567 |
IH 410 |
STP 2021(486)MM |
04/08/2021 |
11/15/2023 |
SURF/ROADWAY RESTOR |
AUSTIN BRIDGE & ROAD SERVICES, LP($22,297,586) |
|
0915-00-235 |
BEXAR |
SAN ANTONIO |
$1,496,202 |
VA |
F 2021(487) |
04/08/2021 |
11/15/2023 |
TRAF SIGNAL IMPRVS |
D&G ENERGY CORPORATION($1,609,699) |
|
0915-00-229 |
BEXAR |
SAN ANTONIO |
$1,084,790 |
VA |
C 915-00-229 |
04/08/2021 |
11/15/2023 |
HWY IMPRV |
INTERSTATE BARRICADES & MARKINGS, INC.($916,531) |
|
2452-02-083 |
BEXAR |
SAN ANTONIO |
$166,009,497 |
SL 1604 |
F 2021(488) |
04/07/2021 |
11/15/2023 |
WIDEN ROAD - ADD LANES |
WILLIAMS BROTHERS CONSTRUCTION CO., INC.($148,073,104) |
|
0016-08-039 |
BEXAR |
SAN ANTONIO |
$7,127,370 |
SL 368 |
BR 2021(485) |
04/07/2021 |
11/15/2023 |
BRIDGE REPL |
RELMCO, INC.($6,974,797) |
|
6376-06-001 |
ATASCOSA |
SAN ANTONIO |
$109,614 |
US0281 |
BPM - 637606001 |
03/17/2021 |
11/15/2023 |
RIPRAP REPAIR |
DBI SERVICES, LLC($99,804) |
|
6369-05-001 |
BEXAR |
SAN ANTONIO |
$159,995 |
MR0681 |
RMC - 636905001 |
03/17/2021 |
11/15/2023 |
OVERLAY. |
TEXAS MATERIALS GROUP, INC.($104,732) |
|
6376-05-001 |
ATASCOSA |
SAN ANTONIO |
$63,412 |
SH0016 |
BPM - 637605001 |
03/17/2021 |
11/15/2023 |
BRIDGE SUBSTRUCT REPAIR |
SJ&J CONSTRUCTION, LLC($60,160) |
|
6369-06-001 |
BEXAR |
SAN ANTONIO |
$101,750 |
IH0035 |
BPM - 636906001 |
03/17/2021 |
11/15/2023 |
BRIDGE PREVENT MAINT |
DOUBLE L CONTRACTING, LLC($67,990) |
|
0521-06-138 |
BEXAR |
SAN ANTONIO |
$108,044,335 |
IH 410 |
F 2021(404) |
03/05/2021 |
11/15/2023 |
CONSTRUCT DIRECT CONNECTORS |
WILLIAMS BROTHERS CONSTRUCTION CO., INC.($100,202,671) |
|
0017-02-080 |
BEXAR |
SAN ANTONIO |
$682,061 |
IH 35 |
NH 2021(203) |
03/04/2021 |
11/15/2023 |
INSTL WRONG WAY DRIVER TECH AT VARIOUS LOCATIONS |
FLORIDA TRAFFIC CONTROL DEVICES, INC.($486,979) |
|
0915-12-664 |
BEXAR |
SAN ANTONIO |
$4,939,085 |
VA |
CM 2021(405) |
03/04/2021 |
11/15/2023 |
INSTL ADVANCED TRAF MGT SYSTEM |
SICE, INC.($5,046,004) |
|
6372-79-001 |
KERR |
SAN ANTONIO |
$165,360 |
MR0674 |
RMC - 637279001 |
02/17/2021 |
09/26/2024 |
GRADING, FLEXIBLE BASE AND SEAL COAT |
TIERRA LEASE SERVICE, LLC($189,897) |
|
0915-00-224 |
BEXAR |
SAN ANTONIO |
$2,172,495 |
VA |
STP 2021(361) |
02/05/2021 |
11/15/2023 |
INTERS OPERATIONAL IMPRVS |
RELMCO, INC.($2,764,875) |
|
6359-10-001 |
GUADALUPE |
SAN ANTONIO |
$272,993 |
SH0046 |
TMC - 635910001 |
02/05/2021 |
11/15/2023 |
DELINEATORS SEGUIN RDC (MATERIAL ONLY) |
CENTERLINE SUPPLY, INC.($417,027) |
|
0915-12-633 |
BEXAR |
SAN ANTONIO |
$933,602 |
CS |
STP 2021(363)HESG |
02/04/2021 |
11/15/2023 |
HAZARD ELIM & SAFETY |
E-Z BEL CONSTRUCTION, LLC($872,525) |
|
0915-00-228 |
BEXAR |
SAN ANTONIO |
$1,496,283 |
VA |
STP 2021(362) |
02/04/2021 |
11/15/2023 |
DISTRICTWIDE NON-SITE SPECIFIC TRAF SIG-FY2021 |
THE LEVY COMPANY, INC.($1,625,676) |