Control County District Estimate Highway Project Date Added Type Low bidder
0774-01-019 ERATH FORT WORTH $9,105,558 FM 219 C 774-1-19 04/07/2022 09/24/2024 REHAB EXIST ROADWAY JAY MILLS CONTRACTING, INCORPORATED($8,247,728)
1054-01-009 BOSQUE WACO $6,192,286 FM 219 C 1054-1-9 09/01/2021 11/15/2023 SEAL COAT BRANNAN PAVING CO., LTD.($5,391,495)
1054-02-023 BOSQUE WACO $13,280,170 FM 219 F 2023(363) 12/01/2022 09/24/2024 REHAB EXIST ROADWAY BIG CREEK CONSTRUCTION, LTD.($10,387,524)
0724-02-020 BOSQUE WACO $7,591,387 FM 219 BR 2B24(133) 06/06/2024 04/25/2024 REPLACE BRIDGE AND APPROACHES KNIFE RIVER CORPORATION - SOUTH($6,464,517)