0006-01-100 |
MITCHELL |
ABILENE |
$292,021 |
IH 20 |
NH 2019(391) |
01/09/2019 |
11/15/2023 |
OBLITERATE EXIST PAVMT |
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.($328,278) |
|
0007-10-066 |
PALO PINTO |
FORT WORTH |
$470,280 |
US 180 |
STP 2019(215) |
01/09/2019 |
11/15/2023 |
CLEAN DITCH & GABION MATTRESS |
TALBRAN ENTERPRISES LLC($419,010) |
|
0008-03-120 |
PARKER |
FORT WORTH |
$2,579,320 |
IH 20 |
C 8-3-120 |
01/09/2019 |
11/15/2023 |
GR, BS, DR, PAV |
ALTUS CONSTRUCTION LLC($3,434,712) |
|
0008-07-035 |
TARRANT |
FORT WORTH |
$5,883,084 |
SH 180 |
C 8-7-35 |
01/09/2019 |
11/15/2023 |
BASE RPR, MILL, OVERLAY, PAVMT MARK |
AUSTIN BRIDGE & ROAD SERVICES, LP($6,444,576) |
|
0009-11-245 |
DALLAS |
DALLAS |
$1,415,897 |
IH 30 |
C 9-11-245 |
01/09/2019 |
11/15/2023 |
FULL DEPTH CONC REPAIR |
O. TREVINO CONSTRUCTION, LLC($1,336,468) |
|
0015-08-142 |
WILLIAMSON |
AUSTIN |
$14,305,404 |
IH 35 |
NH 2019(605) |
01/09/2019 |
11/15/2023 |
GRADING, BASE, HMACP, PVMRK & SIGNS |
DAN WILLIAMS COMPANY($13,145,763) |
|
0016-01-125 |
TRAVIS |
AUSTIN |
$1,087,037 |
SL 275 |
STP 2019(380) |
01/09/2019 |
11/15/2023 |
TOM OVERLAY WITH EDGE MILLING |
AUSTIN MATERIALS, LLC($1,030,070) |
|
0018-05-095 |
WEBB |
LAREDO |
$12,388,126 |
IH 35 |
NH 2019(375) |
01/09/2019 |
11/15/2023 |
RESURF OF EXIST HWY |
ANDERSON COLUMBIA CO., INC.($12,256,476) |
|
0043-08-076 |
WICHITA |
WICHITA FALLS |
$976,809 |
US 287 |
STP 2019(305)HES |
01/09/2019 |
11/15/2023 |
SAFETY LIGHTING |
VACA UNDERGROUND UTILITIES INC($1,090,137) |
|
0043-08-078 |
WICHITA |
WICHITA FALLS |
$487,147 |
US 287 |
STP 2019(438)HES |
01/09/2019 |
11/15/2023 |
HIGH FRICTION SURF TREATMENT |
THE TRUESDELL CORPORATION($433,433) |
|
0089-07-156 |
WHARTON |
YOAKUM |
$295,465 |
US 59 |
C 89-7-156 |
01/09/2019 |
11/15/2023 |
SLOPE REPAIR |
TREVWAY, INC.($286,694) |
|
0113-07-066 |
HAYS |
AUSTIN |
$515,639 |
US 290 |
STP 2019(105)HES |
01/09/2019 |
11/15/2023 |
PROFILE EDGELINE AND CENTERLINE MRK |
TRP CONSTRUCTION GROUP, LLC($526,358) |
|
0113-07-069 |
HAYS |
AUSTIN |
$490,763 |
US 290 |
STP 2019(378)HES |
01/09/2019 |
11/15/2023 |
IMPROVE TRAF SIG |
THE LEVY COMPANY, INC.($436,563) |
|
0128-04-038 |
MCCULLOCH |
BROWNWOOD |
$6,691,606 |
US 190 |
NH 2019(433) |
01/09/2019 |
11/15/2023 |
RECON ROADWAY |
BIG CREEK CONSTRUCTION, LTD.($8,589,804) |
|
0134-03-032 |
YOUNG |
WICHITA FALLS |
$2,714,623 |
US 380 |
STP 2019(439) |
01/09/2019 |
11/15/2023 |
LEVEL UP AND OVERLAY |
JAGOE-PUBLIC COMPANY($2,678,507) |
|
0138-06-044 |
NACOGDOCHES |
LUFKIN |
$3,720,758 |
US 259 |
C 138-6-44 |
01/09/2019 |
11/15/2023 |
PLANE, OCST AND PFC |
DREWERY CONSTRUCTION COMPANY, INCORPORATED($3,341,270) |
|
0139-05-043 |
REEVES |
ODESSA |
$23,840,072 |
US 285 |
STP 2019(387) |
01/09/2019 |
11/15/2023 |
ROADWAY REHAB |
FNF CONSTRUCTION, INC.($18,885,091) |
|
0146-06-030 |
FOARD |
CHILDRESS |
$4,065,361 |
US 70 |
STP 2019(404) |
01/09/2019 |
11/15/2023 |
REHAB OF EXIST ROADWAY |
DUININCK, INC.($4,375,237) |
|
0155-03-037 |
GOLIAD |
CORPUS CHRISTI |
$2,949,650 |
US 183 |
BR 1502(573) |
01/09/2019 |
11/15/2023 |
BRIDGE REPL |
RELMCO, INC.($3,587,103) |
|
0177-07-114 |
HARRIS |
HOUSTON |
$2,789,323 |
IH 69 |
NH 1802(596) |
01/09/2019 |
11/15/2023 |
BRIDGE DECK REPL |
ISI CONTRACTING, INC.($2,711,904) |
|
0184-03-038 |
BELL |
WACO |
$1,194,128 |
SH 53 |
C 184-3-38 |
01/09/2019 |
11/15/2023 |
MILL/OVLY |
LONE STAR PAVING COMPANY($1,032,768) |
|
0186-04-032 |
BURLESON |
BRYAN |
$129,129 |
SH 36 |
STP 2018(994) |
01/09/2019 |
11/15/2023 |
LANDSCAPE AND AESTHETICS DEVELOPMENT |
GREEN SOURCE ENVIRONMENTAL SOLUTIONS, INC.($118,990) |
|
0200-10-067 |
HARDIN |
BEAUMONT |
$2,168,704 |
US 69 |
NH 1802(598) |
01/09/2019 |
11/15/2023 |
GR, BS, STR, PVMT, SIGN |
TEXAS MATERIALS GROUP, INC.($1,853,960) |
|
0271-07-322 |
HARRIS |
HOUSTON |
$657,889 |
IH 10 |
C 271-7-322 |
01/09/2019 |
11/15/2023 |
INSTL STRIPING |
PMI PAVEMENT MARKING, LLC($529,716) |
|
0275-04-052 |
CARSON |
AMARILLO |
$7,990,543 |
IH 40 |
C 275-4-52 |
01/09/2019 |
11/15/2023 |
ACP OVERLAY,CRCP REPAIR, MBGF, AND STRIPING. |
KIEWIT INFRASTRUCTURE SOUTH CO.($8,012,745) |
|
0301-03-026 |
FRIO |
SAN ANTONIO |
$1,362,455 |
SH 85 |
C 301-3-26 |
01/09/2019 |
11/15/2023 |
REHAB EXIST ROADWAY |
ANDERSON COLUMBIA CO., INC.($1,754,396) |
|
0437-02-017 |
CALLAHAN |
ABILENE |
$3,681,738 |
US 283 |
STP 2019(394) |
01/09/2019 |
11/15/2023 |
3"OVERLAY |
J. H. STRAIN & SONS, INC.($3,259,093) |
|
0471-05-046 |
BASTROP |
AUSTIN |
$548,351 |
SH 21 |
STP 2019(386)HES |
01/09/2019 |
11/15/2023 |
INSTL TRAF SIGNAL |
THE LEVY COMPANY, INC.($568,729) |
|
0495-07-076 |
GREGG |
TYLER |
$1,774,088 |
IH 20 |
NH 2019(436) |
01/09/2019 |
11/15/2023 |
TBPFC&ACP SURF,PLNG,SHLDR TXTR, PV MK |
EAST TEXAS BRIDGE, INC.($1,878,815) |
|
0510-04-013 |
FANNIN |
PARIS |
$14,983,579 |
FM 898 |
STP 2019(302) |
01/09/2019 |
11/15/2023 |
REHAB OF EXIST ROAD |
D. L. LENNON INCORPORATED - CONTRACTOR($12,209,810) |
|
0687-01-013 |
GONZALES |
YOAKUM |
$2,337,553 |
FM 77 |
BR 2019(418) |
01/09/2019 |
11/15/2023 |
REPLACE BRIDGE AND APPROACHES |
HILL COUNTRY BRIDGE, INC.($1,928,660) |
|
0836-02-075 |
BELL |
WACO |
$317,716 |
SH 195 |
STP 2019(406)HES |
01/09/2019 |
11/15/2023 |
INSTLL SGNLS AND SGNS |
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.($288,045) |
|
0907-00-173 |
TOM GREEN |
SAN ANGELO |
$1,354,953 |
VA |
STP 2019(397) |
01/09/2019 |
11/15/2023 |
PAVMT MRK |
VIZCAINO, L.P.($1,514,295) |
|
0910-00-107 |
SMITH |
TYLER |
$1,947,371 |
VA |
STP 2019(324) |
01/09/2019 |
11/15/2023 |
THERMOPLASTIC PAVMT MRK |
CENTERLINE TECHNOLOGIES, LLC($1,530,350) |
|
0914-00-411 |
TRAVIS |
AUSTIN |
$2,258,762 |
VA |
STP 2019(381) |
01/09/2019 |
11/15/2023 |
INSTL OR REBUILD TRAF SIG |
THE LEVY COMPANY, INC.($2,524,409) |
|
0918-11-089 |
KAUFMAN |
DALLAS |
$747,487 |
CR |
BR 2017(103) |
01/09/2019 |
11/15/2023 |
REPLACE BRIDGE AND APPROACHES |
HIGHWAY 19 CONSTRUCTION LLC($641,517) |
|
0926-01-023 |
CHEROKEE |
TYLER |
$734,897 |
FM 343 |
STP 2019(429)HES |
01/09/2019 |
11/15/2023 |
STRUCTS & DRAINAGE IMPRVS |
HIGHWAY 19 CONSTRUCTION LLC($638,598) |
|
1186-01-097 |
TRAVIS |
AUSTIN |
$367,128 |
FM 969 |
STP 2019(493)HES |
01/09/2019 |
11/15/2023 |
IMPROVE TRAF SIGNAL,INST FLASHING YELLOW ARROW |
THE LEVY COMPANY, INC.($360,089) |
|
1188-02-087 |
MIDLAND |
ODESSA |
$22,255,624 |
SL 250 |
STP 2019(442) |
01/09/2019 |
11/15/2023 |
CONSTRUCT NEW INTERCHANGE |
JONES BROS. DIRT & PAVING CONTRACTORS, INC.($24,267,703) |
|
1192-01-024 |
MCLENNAN |
WACO |
$6,869,586 |
FM 939 |
STP 2017(936) |
01/09/2019 |
11/15/2023 |
WDN, GR, BS, SURF, ADD SHLDRS |
KNIFE RIVER CORPORATION - SOUTH($6,431,694) |
|
1310-01-027 |
DENTON |
DALLAS |
$3,666,125 |
FM 407 |
BR 2019(492) |
01/09/2019 |
11/15/2023 |
REPLACE BRIDGE AND APPROACHES |
HIGHWAY 19 CONSTRUCTION LLC($3,324,126) |
|
1418-01-012 |
WALLER |
HOUSTON |
$1,439,222 |
FM 1489 |
C 1418-1-12 |
01/09/2019 |
11/15/2023 |
BASE REPAIR,ACP OVERLAY AND PAVMT MRK |
ANGEL BROTHERS HOLDINGS CORP.($1,597,058) |
|
1575-04-017 |
HARRISON |
ATLANTA |
$307,349 |
SL 390 |
STP 2019(587)HES |
01/09/2019 |
11/15/2023 |
INSTL TRAF SIGNAL |
STRIPING TECHNOLOGY, L.P.($284,476) |
|
2103-01-035 |
WILLIAMSON |
AUSTIN |
$1,384,336 |
RM 2243 |
STP 2019(382) |
01/09/2019 |
11/15/2023 |
DEPTH REPAIR, UNDERSEAL & THIN OVERLAY |
ANGEL BROTHERS HOLDINGS CORP.($1,310,876) |
|
2208-02-022 |
DALLAS |
DALLAS |
$2,586,374 |
SS 303 |
C 2208-2-22 |
01/09/2019 |
11/15/2023 |
FULL DEPTH REPAIR CP, OVERLAY & PAVMT MRK |
O. TREVINO CONSTRUCTION, LLC($2,756,289) |
|
2363-01-007 |
ROCKWALL |
DALLAS |
$2,874,972 |
FM 2453 |
C 2363-1-7 |
01/09/2019 |
11/15/2023 |
PROVIDE ADDITIONAL PAVED SURF WIDTH |
A. K. GILLIS & SONS, INC.($2,753,945) |
|
2635-05-001 |
RANDALL |
AMARILLO |
$46,878,849 |
SL 335 |
NH 2019(411) |
01/09/2019 |
11/15/2023 |
B-2 PHASE I: CONSTRUCT FRT RDS FOR FUTURE FREEWAY |
ALLEN BUTLER CONSTRUCTION, INC.($45,797,691) |
|
3240-01-019 |
WOOD |
TYLER |
$5,870,280 |
SL 564 |
STP 2019(323) |
01/09/2019 |
11/15/2023 |
PLANING,PVMT RPR,ACP,OCST,PFS,MBGF,PV MK |
REYNOLDS & KAY, LTD.($5,773,807) |
|
6330-00-001 |
TARRANT |
FORT WORTH |
$314,406 |
IH0030 |
RMC - 633000001 |
01/09/2019 |
11/15/2023 |
CLEANING AND RESHAPING DITCHES |
TEXAS DRAINAGE INC.($246,995) |
|
6330-78-001 |
WISE |
FORT WORTH |
$1,912,730 |
FM0051 |
RMC - 633078001 |
01/09/2019 |
11/15/2023 |
FLEXIBLE PAVMT REPAIR |
JAGOE-PUBLIC COMPANY($1,887,509) |
|
6332-52-001 |
HARRIS |
HOUSTON |
$2,189,092 |
IH0010 |
RMC - 633252001 |
01/09/2019 |
11/15/2023 |
REPLACE EXIST OVH & GROUND MOUNT LARGE SIGNS |
BATTERSON, LLP($1,820,450) |
|
6333-78-001 |
JEFFERSON |
BEAUMONT |
$624,360 |
US0069 |
RMC - 633378001 |
01/09/2019 |
11/15/2023 |
FULL DEPTH CONC PAVMT REPAIR |
TALBRAN ENTERPRISES LLC($582,750) |
|
6333-83-001 |
GONZALES |
YOAKUM |
$589,994 |
IH0010 |
RMC - 633383001 |
01/09/2019 |
11/15/2023 |
ON CALL LUMINAIRE/TRAF SIGNAL/GUIDE SIGN REPAIR |
THIRD COAST SERVICES LLC($925,501) |
|
6334-97-001 |
BAYLOR |
WICHITA FALLS |
$530,499 |
SH0114 |
RMC - 633497001 |
01/09/2019 |
11/15/2023 |
METAL BEAM GUARD FENCE UPGRADE |
3LW CIVIL LLC($528,670) |
|
6335-54-001 |
JASPER |
BEAUMONT |
$605,817 |
SH0063 |
RMC - 633554001 |
01/09/2019 |
11/15/2023 |
MILL & INLAY |
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.($570,205) |
|
6336-47-001 |
PARKER |
FORT WORTH |
$2,859,021 |
IH0020 |
RMC - 633647001 |
01/09/2019 |
11/15/2023 |
FLEXIBLE PAV STR REPAIR (MILL AND INLAY) |
NORTHEASTERN PAVERS, LLC($2,439,851) |
|
6336-61-001 |
MCLENNAN |
WACO |
$1,543,968 |
US0084 |
RMC - 633661001 |
01/09/2019 |
11/15/2023 |
SPALL & FULL DEPTH CONC REPAIR |
CROSS PLUS CONSTRUCTION, LLC($1,496,038) |
|
6337-04-001 |
DENTON |
DALLAS |
$390,000 |
IH0035 |
RMC - 633704001 |
01/09/2019 |
11/15/2023 |
POTHOLE REPAIR |
BRYDL CONTRACTING, INC.($463,500) |
|
6337-35-001 |
HARDIN |
BEAUMONT |
$726,658 |
FM0770 |
RMC - 633735001 |
01/09/2019 |
11/15/2023 |
FLEXIBLE PAVMT STRUCT REPAIR |
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.($768,059) |
|
6337-37-001 |
DALLAS |
DALLAS |
$534,099 |
US0067 |
RMC - 633737001 |
01/09/2019 |
11/15/2023 |
RETROREFLECTORIZED PAVMT MRK & MARKERS |
TRP CONSTRUCTION GROUP, LLC($481,097) |
|
6337-40-001 |
KAUFMAN |
DALLAS |
$879,114 |
IH0020 |
RMC - 633740001 |
01/09/2019 |
11/15/2023 |
VEGETATION MGT (NORTH SIDE) |
CROSS PLUS CONSTRUCTION, LLC($1,030,803) |
|
6337-44-001 |
CHILDRESS |
CHILDRESS |
$624,767 |
US0287 |
BPM - 633744001 |
01/09/2019 |
11/15/2023 |
2019 BPM PROJECT |
RESTEK, INC.($584,840) |
|
6337-64-001 |
MENARD |
SAN ANGELO |
$1,553,200 |
RM1773 |
RMC - 633764001 |
01/09/2019 |
11/15/2023 |
WIDENING OF ROADWAY |
ALLEN KELLER COMPANY($2,258,273) |
|
6338-00-001 |
GUADALUPE |
SAN ANTONIO |
$617,120 |
IH0010 |
RMC - 633800001 |
01/09/2019 |
11/15/2023 |
MOW HWY ROW |
SOUTH TEXAS MAINTENANCE, INC.($601,862) |
|
6338-01-001 |
KERR |
SAN ANTONIO |
$534,858 |
IH0010 |
RMC - 633801001 |
01/09/2019 |
11/15/2023 |
MOW AND LITTER RMVL |
SOUTH TEXAS MAINTENANCE, INC.($656,697) |
|
6338-02-001 |
MEDINA |
SAN ANTONIO |
$698,732 |
US0090 |
RMC - 633802001 |
01/09/2019 |
11/15/2023 |
MOW AND LITTER RMVL |
R&M INCORPORATED($665,750) |
|
6338-03-001 |
KENDALL |
SAN ANTONIO |
$492,590 |
IH0010 |
RMC - 633803001 |
01/09/2019 |
11/15/2023 |
MOW |
SOUTH TEXAS MAINTENANCE, INC.($558,476) |
|
6338-04-001 |
BANDERA |
SAN ANTONIO |
$337,220 |
SH0016 |
RMC - 633804001 |
01/09/2019 |
11/15/2023 |
MOW |
CLASSIC IRRIGATION & LANDSCAPE LLC($333,050) |
|
6338-55-001 |
JEFFERSON |
BEAUMONT |
$154,748 |
US0090 |
BPM - 633855001 |
01/09/2019 |
11/15/2023 |
RIPRAP AND SCOUR REPAIRS |
WIDGEON CONSTRUCTION, INC.($141,495) |
|
6338-67-001 |
HUNT |
PARIS |
$337,560 |
IH0030 |
RMC - 633867001 |
01/09/2019 |
11/15/2023 |
DEBRIS RMVL |
CATOCON, INC.($298,730) |
|
6338-92-001 |
GALVESTON |
HOUSTON |
$404,343 |
SH0146 |
RMC - 633892001 |
01/09/2019 |
11/15/2023 |
PUMP STATION & DRAINAGE SYSTEM CLEANING |
AIMS COMPANIES($397,399) |
|
6338-95-001 |
HARRIS |
HOUSTON |
$772,249 |
SH0249 |
RMC - 633895001 |
01/09/2019 |
11/15/2023 |
FULL DEPTH CONC & ASPH REPAIR |
MAIN LANE INDUSTRIES LTD.($733,405) |
|
6339-33-001 |
VAN ZANDT |
TYLER |
$486,800 |
SH0019 |
RMC - 633933001 |
01/09/2019 |
11/15/2023 |
TREE RMVL |
CATOCON, INC.($359,400) |
|
6339-35-001 |
WOOD |
TYLER |
$758,400 |
SH0037 |
RMC - 633935001 |
01/09/2019 |
11/15/2023 |
TREE RMVL |
CATOCON, INC.($656,928) |
|
6339-47-001 |
EL PASO |
EL PASO |
$561,178 |
IH0010 |
RMC - 633947001 |
01/09/2019 |
11/15/2023 |
METAL BEAM GUARD FENCE |
APACHE BARRICADE & SIGN($647,900) |
|
6339-72-001 |
EL PASO |
EL PASO |
$446,650 |
IH0010 |
RMC - 633972001 |
01/09/2019 |
11/15/2023 |
BARRICADES, SIGNS AND TRAF CONTROL |
NIXON ENGINEERING($401,465) |
|
6340-03-001 |
VICTORIA |
YOAKUM |
$572,140 |
US0059 |
RMC - 634003001 |
01/09/2019 |
11/15/2023 |
CRACK SEAL SPRING |
D & M CONTRACTORS, LLC($588,310) |
|
6340-54-001 |
VICTORIA |
YOAKUM |
$589,994 |
US0059 |
RMC - 634054001 |
01/09/2019 |
11/15/2023 |
ON CALL LUMINAIRE AND SIGNS |
THIRD COAST SERVICES LLC($925,501) |