0519-02-019 |
HILL |
WACO |
$16,611,185 |
SH 174 |
BR 2022(480) |
05/05/2022 |
08/31/2024 |
REPLACE BRIDGES AND APPROACHES |
A. L. HELMCAMP, INC.($23,690,787) |
|
0019-03-028 |
HILL |
WACO |
$6,082,873 |
SH 171 |
STP 2022(886)HES |
08/03/2022 |
11/15/2023 |
HAZARD ELIM & SAFETY |
BEAR CREEK CONTRACTING, LLC($5,859,953) |
|
0596-01-021 |
HILL |
WACO |
$854,447 |
FM 66 |
STP 1902(017)HRR |
08/06/2019 |
11/15/2023 |
SAFETY TREAT FIXED OBJECTS |
BEAR CREEK CONTRACTING, LLC($849,409) |
|
6384-29-001 |
HILL |
WACO |
$598,854 |
SH0081 |
RMC - 638429001 |
01/07/2022 |
11/15/2023 |
BRIDGE PREVENT MAINT |
BECK-REIT & SONS, LTD.($532,172) |
|
6332-84-001 |
HILL |
WACO |
$494,455 |
SH0022 |
BPM - 633284001 |
12/06/2018 |
11/15/2023 |
BRIDGE PREVENT MAINT |
BECK-REIT & SONS, LTD.($478,750) |
|
6380-22-001 |
HILL |
WACO |
$546,887 |
SH0081 |
MMC - 638022001 |
05/06/2021 |
11/15/2023 |
HOT MIX |
BIG CREEK CONSTRUCTION, LTD.($458,550) |
|
6339-87-001 |
HILL |
WACO |
$1,510,178 |
FM0744 |
RMC - 633987001 |
03/05/2019 |
11/15/2023 |
MILL AND INLAY |
BIG CREEK CONSTRUCTION, LTD.($2,049,550) |
|
0596-01-023 |
HILL |
WACO |
$2,407,365 |
FM 66 |
C 596-1-23 |
01/06/2022 |
11/15/2023 |
REHAB ROADWAY AND ADD CONC PAVMT |
BIG CREEK CONSTRUCTION, LTD.($2,787,393) |
|
0121-03-063 |
HILL |
WACO |
$962,110 |
SH 22 |
NH 2021(080) |
11/05/2020 |
11/15/2023 |
REHAB OF EXIST ROAD |
BIG CREEK CONSTRUCTION, LTD.($1,051,928) |
|
1190-02-018 |
HILL |
WACO |
$5,397,006 |
FM 933 |
F 2021(910) |
07/02/2021 |
11/15/2023 |
SURF/ROADWAY RESTOR |
BIG CREEK CONSTRUCTION, LTD.($4,587,557) |
|
1831-01-019 |
HILL |
WACO |
$2,335,604 |
FM 934 |
STP 2017(599) |
02/03/2017 |
11/15/2023 |
WDN, GR, BS, SURF, ADD SHLDRS |
BIG CREEK CONSTRUCTION, LTD.($2,487,232) |
|
0014-24-065 |
HILL |
WACO |
$6,546,206 |
IH 35 |
F 2023(619) |
04/04/2023 |
09/24/2024 |
SURF/ROADWAY RESTOR |
BIG CREEK CONSTRUCTION, LTD.($6,648,202) |
|
6341-74-001 |
HILL |
WACO |
$999,951 |
SH0022 |
RMC - 634174001 |
08/07/2019 |
11/15/2023 |
BASE FAILURE PAVMT REPAIR |
BIG CREEK CONSTRUCTION, LTD.($1,425,926) |
|
6467-50-001 |
HILL |
WACO |
$1,696,600 |
SH0081 |
MMC - 646750001 |
08/01/2024 |
06/26/2024 |
HOT MIX |
BIG CREEK CONSTRUCTION, LTD.($1,778,575) |
|
0162-13-002 |
HILL |
WACO |
$9,439,338 |
SH 31 |
F 2025(088) |
09/05/2024 |
07/25/2024 |
SURF/ROADWAY RESTOR |
BIG CREEK CONSTRUCTION, LTD.($7,287,640) |
|
1662-02-013 |
HILL |
WACO |
$2,652,025 |
FM 339 |
F 2023(278) |
12/02/2022 |
09/24/2024 |
REHAB EXIST ROADWAY |
BIG CREEK CONSTRUCTION, LTD.($2,487,780) |
|
3030-01-010 |
HILL |
WACO |
$12,787,432 |
FM 2959 |
C 3030-1-10 |
01/04/2024 |
11/23/2023 |
WIDEN ROAD - ADD SHOULDERS |
BIG CREEK CONSTRUCTION, LTD.($12,787,366) |
|
0014-07-101 |
HILL |
WACO |
$2,727,202 |
SH 81 |
F 2022(477) |
05/04/2022 |
08/31/2024 |
MILL AND OVERLAY |
BIG CREEK CONSTRUCTION, LTD.($3,020,549) |
|
6469-80-001 |
HILL |
WACO |
$3,575,843 |
IH0035 |
RMC - 646980001 |
09/05/2024 |
07/30/2024 |
PAVMT MRK |
CENTERLINE TECHNOLOGIES, LLC($2,640,060) |
|
6389-03-001 |
HILL |
WACO |
$405,824 |
SH0081 |
RMC - 638903001 |
11/04/2021 |
11/15/2023 |
MOW HWY RIGHT OF WAY |
CEN-TEX IRRIGATION SYSTEMS, INC.($474,772) |
|
6472-28-001 |
HILL |
WACO |
$605,669 |
FM0934 |
RMC - 647228001 |
11/13/2024 |
10/15/2024 |
MOW HWY RIGHT OF WAY |
CEN-TEX IRRIGATION SYSTEMS, INC.($420,860) |
|
6339-84-001 |
HILL |
WACO |
$283,428 |
SH0022 |
RMC - 633984001 |
12/12/2018 |
11/15/2023 |
COUNTY WIDE MOW & LITTER RMVL |
CEN-TEX IRRIGATION SYSTEMS, INC.($329,765) |
|
6352-94-001 |
HILL |
WACO |
$330,915 |
SH0022 |
RMC - 635294001 |
12/04/2019 |
11/15/2023 |
MOW AND LITTER RMVL |
CEN-TEX IRRIGATION SYSTEMS, INC.($390,764) |
|
6455-41-001 |
HILL |
WACO |
$607,829 |
SH0171 |
RMC - 645541001 |
11/01/2023 |
11/15/2023 |
MOW HWY RIGHT OF WAY |
CEN-TEX IRRIGATION SYSTEMS, INC.($611,847) |
|
6369-30-001 |
HILL |
WACO |
$360,384 |
SH0022 |
RMC - 636930001 |
12/02/2020 |
11/15/2023 |
MOW AND LITTER RMVL |
CEN-TEX IRRIGATION SYSTEMS, INC.($402,884) |
|
6319-12-001 |
HILL |
WACO |
$566,400 |
SH0022 |
RMC - 631912001 |
08/09/2017 |
11/15/2023 |
CRACK SEAL - HOT APPLICATION |
CHAMPION INFRASTRUCTURE, LLC($422,071) |
|
0209-06-041 |
HILL |
WACO |
$7,252,063 |
FM 310 |
F 2025(086) |
09/06/2024 |
07/26/2024 |
SEAL COAT |
CLARK CONSTRUCTION OF TEXAS, INC.($7,292,707) |
|
0014-17-078 |
HILL |
WACO |
$5,455,088 |
FM 1242 |
F 2022(065) |
09/01/2021 |
11/15/2023 |
SEAL COAT |
COX PAVING OF TEXAS, INC.($4,783,740) |
|
6347-54-001 |
HILL |
WACO |
$372,900 |
FM0308 |
RMC - 634754001 |
08/07/2019 |
11/15/2023 |
TREE TRIM,BRUSH,DRIFTWOOD AND DEBRIS RMVL |
CROSS PLUS CONSTRUCTION, LLC($336,502) |
|
0014-07-103 |
HILL |
WACO |
$513,738 |
SH 81 |
STP 1902(129)HES |
08/07/2019 |
11/15/2023 |
INSTL CABLE MEDIAN BARRIER |
CROSS PLUS CONSTRUCTION, LLC($482,159) |
|
6333-46-001 |
HILL |
WACO |
$397,915 |
SH0171 |
RMC - 633346001 |
11/07/2018 |
11/15/2023 |
DRIFTWOOD & DEBRIS RMVL |
CROSS PLUS CONSTRUCTION, LLC($410,990) |
|
6362-81-001 |
HILL |
WACO |
$532,565 |
FM0933 |
RMC - 636281001 |
08/05/2020 |
11/15/2023 |
CRACK SEAL |
D & M CONTRACTORS, LLC($515,051) |
|
6331-63-001 |
HILL |
WACO |
$552,706 |
FM1946 |
RMC - 633163001 |
08/07/2018 |
11/15/2023 |
HOT APPLICATION CRACK SEAL |
D & M CONTRACTORS, LLC($425,927) |
|
6401-08-001 |
HILL |
WACO |
$527,587 |
SH0022 |
RMC - 640108001 |
08/04/2022 |
11/15/2023 |
CRACK SEAL |
D & M CONTRACTORS, LLC($413,971) |
|
6384-28-001 |
HILL |
WACO |
$494,865 |
FM0934 |
RMC - 638428001 |
08/05/2021 |
11/15/2023 |
CRACK SEAL |
D & M CONTRACTORS, LLC($366,958) |
|
0014-07-105 |
HILL |
WACO |
$4,444,499 |
IH 35 |
STP 2B20(189)HES |
08/05/2020 |
11/15/2023 |
UPGRADING MBGF TO MASH COMPLIANT STANDARDS. |
ENCINO LANDSCAPE, INC.($5,295,309) |
|
0014-23-038 |
HILL |
WACO |
$3,348,708 |
IH 35W |
C 14-23-38 |
07/09/2020 |
11/15/2023 |
ROADWAY LANE DEPARTURE - CABLE MEDIAN BARRIERS |
GRATIOT CONSTRUCTION, LTD.($2,336,016) |
|
6347-31-001 |
HILL |
WACO |
$452,244 |
SH0081 |
RMC - 634731001 |
08/07/2019 |
11/15/2023 |
CRACK SEAL |
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY($419,983) |
|
6306-33-001 |
HILL |
WACO |
$224,483 |
US0077 |
RMC - 630633001 |
07/18/2017 |
11/15/2023 |
TREE TRIM AND TREE RMVL |
KASPARIAN UNDERGROUND, LLC($173,013) |
|
6355-81-001 |
HILL |
WACO |
$1,305,288 |
FM3267 |
RMC - 635581001 |
05/07/2020 |
11/15/2023 |
BASE FAILURE PAVMT REPAIR |
KNIFE RIVER CORPORATION - SOUTH($812,252) |
|
6418-23-001 |
HILL |
WACO |
$286,440 |
SH0081 |
MMC - 641823001 |
08/30/2022 |
11/15/2023 |
HOT MIX |
KNIFE RIVER CORPORATION - SOUTH($296,960) |
|
6399-56-001 |
HILL |
WACO |
$836,030 |
FM0308 |
RMC - 639956001 |
05/04/2022 |
11/15/2023 |
BASE FAILURE PAVMT REPAIR |
KNIFE RIVER CORPORATION - SOUTH($889,845) |
|
0656-01-040 |
HILL |
WACO |
$15,467,709 |
FM 67 |
C 656-1-40 |
04/04/2023 |
09/24/2024 |
REHAB EXIST ROADWAY |
KNIFE RIVER CORPORATION - SOUTH($17,279,323) |
|
6425-52-001 |
HILL |
WACO |
$877,000 |
SH0022 |
MMC - 642552001 |
12/02/2022 |
11/15/2023 |
HOT MIX |
KNIFE RIVER CORPORATION - SOUTH($905,940) |
|
0596-01-019 |
HILL |
WACO |
$2,951,503 |
FM 66 |
BR 2024(986) |
05/03/2024 |
03/22/2024 |
REPL BR & APPRS |
KNIFE RIVER CORPORATION - SOUTH($2,469,349) |
|
6434-78-001 |
HILL |
WACO |
$869,000 |
SH0081 |
MMC - 643478001 |
03/08/2023 |
11/15/2023 |
HOT MIX |
KNIFE RIVER CORPORATION - SOUTH($874,560) |
|
0834-02-031 |
HILL |
WACO |
$3,558,120 |
FM 308 |
BR 2021(679) |
07/01/2021 |
11/15/2023 |
BRIDGE REPL |
KNIFE RIVER CORPORATION - SOUTH($3,137,766) |
|
6467-42-001 |
HILL |
WACO |
$1,711,110 |
SH0174 |
RMC - 646742001 |
06/06/2024 |
04/29/2024 |
BASE FAILURE PAVMT REPAIR |
KNIFE RIVER CORPORATION - SOUTH($1,363,883) |
|
6379-64-001 |
HILL |
WACO |
$862,510 |
FM0934 |
RMC - 637964001 |
05/05/2021 |
11/15/2023 |
BASE FAILURE PAVMT REPAIR |
NORTHEASTERN PAVERS, LLC($631,827) |
|
0014-05-039 |
HILL |
WACO |
$1,956,234 |
SH 81 |
C 14-5-39 |
07/11/2018 |
11/15/2023 |
MISC SPOT PAVMT REPAIRS |
OLDCASTLE MATERIALS TEXAS, INC.($1,999,585) |
|
6401-10-001 |
HILL |
WACO |
$407,542 |
FM3050 |
RMC - 640110001 |
06/29/2022 |
11/15/2023 |
TREE TRIM AND BRUSH RMVL |
PATHFIELD INVESTMENTS LLC($368,714) |
|
6362-77-001 |
HILL |
WACO |
$390,799 |
FM0310 |
RMC - 636277001 |
07/08/2020 |
11/15/2023 |
TREE TRIM, BRUSH REM, DRIFTWOOD & DEBRIS RMVL |
PATHFIELD INVESTMENTS LLC($362,572) |
|
6469-35-001 |
HILL |
WACO |
$389,374 |
SH0171 |
RMC - 646935001 |
07/09/2024 |
06/05/2024 |
TREE TRIM AND BRUSH RMVL |
PATHFIELD INVESTMENTS LLC($369,470) |
|
6381-65-001 |
HILL |
WACO |
$590,823 |
FM0067 |
RMC - 638165001 |
07/02/2021 |
11/15/2023 |
TREE TRIM AND BRUSH RMVL |
PATHFIELD INVESTMENTS LLC($481,357) |
|
0909-37-068 |
HILL |
WACO |
$769,812 |
CO |
BR 2021(316) |
08/01/2024 |
06/20/2024 |
BRIDGE REPL |
PMCO CONSTRUCTION LLC($759,759) |
|
0909-37-065 |
HILL |
WACO |
$461,541 |
CR |
BR 1802(254) |
04/05/2023 |
11/15/2023 |
BRIDGE REPL |
PMCO CONSTRUCTION LLC($558,558) |
|
0014-06-045 |
HILL |
WACO |
$1,747,846 |
SH 81 |
BR 2023(500) |
03/07/2023 |
08/21/2024 |
BRIDGE MAINT |
PMCO CONSTRUCTION LLC($1,619,000) |
|
0048-09-029 |
HILL |
WACO |
$121,792,371 |
IH 35E |
NH 2019(834) |
05/07/2019 |
11/15/2023 |
WDN, GR, STRS, SURF |
SACYR CONSTRUCTION USA LLC($133,117,086) |
|
6438-11-001 |
HILL |
WACO |
$1,929,546 |
SH0022 |
BPM - 643811001 |
10/05/2023 |
11/15/2023 |
BRIDGE REPAIR |
SCOTT TUCKER CONSTRUCTION COMPANY, LLC($1,654,027) |
|
6460-63-001 |
HILL |
WACO |
$1,118,745 |
SH0022 |
RMC - 646063001 |
03/05/2024 |
01/31/2024 |
BRIDGE JOINT CLEANING AND SEALING |
SCR CIVIL CONSTRUCTION, LLC($825,102) |
|
6393-00-001 |
HILL |
WACO |
$726,596 |
SH0171 |
RMC - 639300001 |
01/06/2022 |
11/15/2023 |
BRIDGE REPAIR |
STRUCTURAL INTEGRITY GROUP LLC($762,432) |
|
0162-02-031 |
HILL |
WACO |
$76,294,194 |
SH 31 |
STP 2009(661) |
07/11/2017 |
11/15/2023 |
GR, STRS & SURF |
SUNDT CONSTRUCTION, INC.($63,963,885) |
|
0014-07-104 |
HILL |
WACO |
$1,547,876 |
IH 35 |
STP 2020(526)HES |
12/03/2019 |
11/15/2023 |
INSTL OF RUMBLE STRIPS |
SURFACE PREPARATION TECHNOLOGIES, LLC($1,195,738) |
|
0121-02-061 |
HILL |
WACO |
$2,285,949 |
SH 22 |
STP 2022(336)HES |
02/03/2022 |
11/15/2023 |
RESURF ROADWAY, MILLED EDGELINE RUMBLE STRIP |
TEXAS MATERIALS GROUP, INC.($2,448,816) |
|
6394-97-001 |
HILL |
WACO |
$286,750 |
SH0081 |
MMC - 639497001 |
01/04/2022 |
09/24/2024 |
HOT MIX |
TEXAS MATERIALS GROUP, INC.($284,727) |
|
6356-88-001 |
HILL |
WACO |
$1,315,343 |
SH0081 |
MMC - 635688001 |
03/04/2020 |
11/15/2023 |
HOT MIX-MATERIAL ONLY |
TEXAS MATERIALS GROUP, INC.($1,393,833) |
|
6432-18-001 |
HILL |
WACO |
$898,973 |
FM1304 |
RMC - 643218001 |
03/08/2023 |
11/15/2023 |
BASE FAILURE PAVMT REPAIR |
TEXAS MATERIALS GROUP, INC.($860,756) |
|
6443-86-001 |
HILL |
WACO |
$1,938,000 |
SH0081 |
MMC - 644386001 |
08/03/2023 |
11/15/2023 |
HOT MIX |
TEXAS MATERIALS GROUP, INC.($1,868,470) |
|
0418-02-035 |
HILL |
WACO |
$12,006,392 |
SH 171 |
C 418-2-35 |
01/05/2024 |
11/24/2023 |
SURF/ROADWAY RESTOR |
TEXAS MATERIALS GROUP, INC.($8,755,570) |
|
0014-07-102 |
HILL |
WACO |
$3,850,809 |
IH 35 |
NH 2020(753) |
03/04/2020 |
11/15/2023 |
OVERLAY |
THE TRUESDELL CORPORATION($3,699,699) |
|
0121-02-062 |
HILL |
WACO |
$362,099 |
SH 22 |
F 2022(888) |
08/04/2022 |
11/15/2023 |
TRAF SIGNAL IMPRVS |
VACA UNDERGROUND UTILITIES INC($383,253) |
|
0209-06-040 |
HILL |
WACO |
$78,002 |
FM 933 |
F 2021(549) |
05/05/2021 |
11/15/2023 |
INSTL INTERS FLASHING BEACON |
WG ENGINEERING & CONSTRUCTION, LLC($114,359) |
|
6389-95-001 |
HILL |
WACO |
$1,126,000 |
US0077 |
MMC - 638995001 |
12/04/2024 |
11/10/2024 |
LIMESTONE ROCK ASPH |
|
|
6472-31-001 |
HILL |
WACO |
$115,718 |
SH0022 |
RMC - 647231001 |
12/03/2024 |
11/10/2024 |
SWEEPING AND DEBRIS RMVL |
|
|
6458-91-001 |
HILL |
WACO |
$52,311 |
SH0022 |
RMC - 645891001 |
12/06/2023 |
11/15/2023 |
CLEANING AND SWEEPING HWYS |
|
|
6473-42-001 |
HILL |
WACO |
$1,580,806 |
SH0022 |
RMC - 647342001 |
12/04/2024 |
11/10/2024 |
BASE FAILURE PAVMT REPAIR |
|