6318-34-001 |
EL PASO |
EL PASO |
$578,302 |
IH0010 |
BPM - 631834001 |
03/07/2018 |
11/15/2023 |
BPM |
INTERNATIONAL EAGLE ENTERPRISES, INC.($585,141) |
|
6339-57-001 |
EL PASO |
EL PASO |
$526,870 |
US0054 |
BPM - 633957001 |
05/08/2020 |
11/15/2023 |
BPM |
MARTINEZ BROS. CONTRACTORS, LLC($485,855) |
|
6377-70-001 |
EL PASO |
EL PASO |
$593,610 |
IH0010 |
BPM - 637770001 |
02/03/2022 |
11/15/2023 |
BRIDGE PREVENT MAINT |
HAWK CONSTRUCTION($545,884) |
|
6435-88-001 |
EL PASO |
EL PASO |
$1,247,490 |
IH0010 |
BPM - 643588001 |
09/06/2024 |
07/30/2024 |
BRIDGE PREVENT MAINT |
INTERNATIONAL EAGLE ENTERPRISES, INC.($1,220,296) |
|
2121-02-159 |
EL PASO |
EL PASO |
$473,458 |
IH 10 |
BR 1802(327) |
07/10/2018 |
11/15/2023 |
UPGRADE BRIDGE AND APPROACH RAILING |
DAN WILLIAMS COMPANY($549,262) |
|
0674-02-011 |
EL PASO |
EL PASO |
$2,217,744 |
FM 76 |
BR 2000(030) |
07/11/2017 |
11/15/2023 |
REPLACE BRIDGES AND APPROACHES |
DAN WILLIAMS COMPANY($2,025,296) |
|
2121-05-046 |
EL PASO |
EL PASO |
$2,613,367 |
IH 10 |
BR 2022(646) |
06/02/2022 |
09/03/2024 |
BRIDGE REPL |
DAN WILLIAMS COMPANY($2,488,273) |
|
0924-00-130 |
EL PASO |
EL PASO |
$1,112,544 |
VA |
BR 2023(519) |
03/07/2023 |
08/21/2024 |
PREVENT MAINT |
DAN WILLIAMS COMPANY($1,135,875) |
|
2121-04-110 |
EL PASO |
EL PASO |
$2,466,921 |
IH 10 |
BR 2023(885) |
06/02/2023 |
11/28/2023 |
BRIDGE REPL |
DAN WILLIAMS COMPANY($2,756,557) |
|
2121-02-162 |
EL PASO |
EL PASO |
$1,092,016 |
IH 10 |
BR 2024(032) |
09/06/2023 |
11/15/2023 |
BRIDGE REPL |
DAN WILLIAMS COMPANY($960,423) |
|
0001-04-099 |
EL PASO |
EL PASO |
$5,745,766 |
US 85 |
BR 2024(837) |
04/04/2024 |
02/22/2024 |
BRIDGE REPL |
DAN WILLIAMS COMPANY($4,910,196) |
|
0001-02-067 |
EL PASO |
EL PASO |
$12,288,172 |
SH 20 |
C 1-2-67 |
06/02/2023 |
11/28/2023 |
REHAB EXIST ROADWAY |
INTERNATIONAL EAGLE ENTERPRISES, INC.($12,401,685) |
|
0001-02-069 |
EL PASO |
EL PASO |
$1,692,784 |
SH 20 |
C 1-2-69 |
08/06/2020 |
11/15/2023 |
PEDESTRIAN SAFETY IMPRVS |
MARTINEZ BROS. CONTRACTORS, LLC($1,665,139) |
|
0001-02-076 |
EL PASO |
EL PASO |
$3,219,859 |
SH 20 |
C 1-2-76 |
06/27/2023 |
11/15/2023 |
HAZARD ELIM & SAFETY |
MARTINEZ BROS. CONTRACTORS, LLC($3,070,094) |
|
0167-02-051 |
EL PASO |
EL PASO |
$2,295,063 |
BU 54-A |
C 167-2-51 |
07/10/2018 |
11/15/2023 |
OVERLAY |
J. A. R. CONCRETE, INC.($1,723,480) |
|
0002-01-108 |
EL PASO |
EL PASO |
$11,404,066 |
SH 20 |
C 2-1-108 |
05/03/2024 |
03/22/2024 |
RESURF ROADWAY |
DAN WILLIAMS COMPANY($8,421,430) |
|
2121-02-171 |
EL PASO |
EL PASO |
$645,428 |
IH 10 |
C 2121-2-171 |
07/09/2020 |
11/15/2023 |
GREEN RIBBON LANDSCAPE IMPRV |
INTERNATIONAL EAGLE ENTERPRISES, INC.($507,007) |
|
2121-02-174 |
EL PASO |
EL PASO |
$2,526,198 |
IH 10 |
C 2121-2-174 |
12/02/2020 |
11/15/2023 |
INSTL OF CONC TRAF BARRIER |
J. A. R. CONCRETE, INC.($2,186,645) |
|
2121-02-174 |
EL PASO |
EL PASO |
$2,536,214 |
IH 10 |
C 2121-2-174 |
08/05/2020 |
11/15/2023 |
INSTL OF CONC TRAF BARRIER |
SYNERGY PROJECT CONTRACTORS, INC.($2,235,502) |
|
2121-03-171 |
EL PASO |
EL PASO |
$4,073,244 |
IH 10 |
C 2121-3-171 |
06/06/2024 |
04/25/2024 |
LANDSCAPE DEVELOPMENT |
EL PASO A.R.C. ELECTRIC, INC.($4,052,804) |
|
2121-03-060 |
EL PASO |
EL PASO |
$10,960,314 |
IH 10 |
C 2121-3-60 |
06/05/2020 |
11/15/2023 |
CONSTRUCT ASPH CONC PVMNT MILL AND INLAY |
DAN WILLIAMS COMPANY($9,796,784) |
|
2121-04-121 |
EL PASO |
EL PASO |
$1,070,953 |
IH 10 |
C 2121-4-121 |
07/01/2021 |
11/15/2023 |
PREVENT MAINT |
PENHALL COMPANY($1,097,606) |
|
2121-04-124 |
EL PASO |
EL PASO |
$1,523,306 |
IH 10 |
C 2121-4-124 |
06/28/2023 |
11/15/2023 |
PREVENT MAINT |
DIAMOND SURFACE, INC.($1,536,930) |
|
2121-04-086 |
EL PASO |
EL PASO |
$2,429,473 |
IH 10 |
C 2121-4-86 |
07/11/2018 |
11/15/2023 |
REHAB |
DAN WILLIAMS COMPANY($1,988,430) |
|
2121-05-051 |
EL PASO |
EL PASO |
$5,397,225 |
IH 10 |
C 2121-5-51 |
07/08/2020 |
11/15/2023 |
INSTL MEDIAN CABLE BARRIER |
LESNA CONSTRUCTION, INC.($4,020,480) |
|
0002-02-061 |
EL PASO |
EL PASO |
$1,960,340 |
SH 20 |
C 2-2-61 |
06/27/2023 |
11/15/2023 |
CONSTRUCT PEDESTRIAN INFRASTRUCT |
INTERNATIONAL EAGLE ENTERPRISES, INC.($1,502,237) |
|
2552-02-034 |
EL PASO |
EL PASO |
$982,043 |
SL 375 |
C 2552-2-34 |
06/04/2020 |
11/15/2023 |
MILL & OVERLAY CLEANING/RESEAL BRIDGE JOINTS |
DAN WILLIAMS COMPANY($777,686) |
|
2552-02-035 |
EL PASO |
EL PASO |
$4,730,247 |
SL 375 |
C 2552-2-35 |
08/04/2021 |
11/15/2023 |
INTERCHANGE IMPRV |
INTERNATIONAL EAGLE ENTERPRISES, INC.($3,808,795) |
|
2552-03-063 |
EL PASO |
EL PASO |
$3,032,389 |
SL 375 |
C 2552-3-63 |
03/07/2018 |
11/15/2023 |
CONSTRUCT 1 NOISE WALLS |
INTERNATIONAL EAGLE ENTERPRISES, INC.($4,497,506) |
|
2552-03-065 |
EL PASO |
EL PASO |
$12,257,957 |
SL 375 |
C 2552-3-65 |
04/04/2024 |
02/22/2024 |
SURF/ROADWAY RESTOR |
DAN WILLIAMS COMPANY($10,150,487) |
|
2552-04-046 |
EL PASO |
EL PASO |
$5,239,157 |
SL 375 |
C 2552-4-46 |
07/02/2021 |
11/15/2023 |
SURF/ROADWAY RESTOR |
J. A. R. CONCRETE, INC.($3,878,272) |
|
3451-01-033 |
EL PASO |
EL PASO |
$14,340,540 |
FM 1281 |
C 3451-1-33 |
04/05/2023 |
11/15/2023 |
REHAB EXIST ROADWAY |
DAN WILLIAMS COMPANY($9,420,481) |
|
3572-01-006 |
EL PASO |
EL PASO |
$838,324 |
SS 6 |
C 3572-1-6 |
07/11/2018 |
11/15/2023 |
MILL AND OVERLAY |
ALLIED PAVING CO.($735,010) |
|
0374-02-120 |
EL PASO |
EL PASO |
$10,656,964 |
US 62 |
C 374-2-120 |
03/05/2024 |
01/23/2024 |
PREVENT MAINT |
INTERNATIONAL EAGLE ENTERPRISES, INC.($9,875,875) |
|
0924-00-105 |
EL PASO |
EL PASO |
$968,876 |
VA |
C 924-00-105 |
04/07/2022 |
09/24/2024 |
BRIDGE MAINT |
MIJELUM, L.L.C.($1,053,915) |
|
0924-00-106 |
EL PASO |
EL PASO |
$3,425,853 |
VA |
C 924-00-106 |
02/04/2022 |
11/15/2023 |
PREVENT MAINT |
CENTERLINE TECHNOLOGIES, LLC($3,068,481) |
|
0924-00-109 |
EL PASO |
EL PASO |
$1,431,813 |
VA |
C 924-00-109 |
03/08/2023 |
08/21/2024 |
BRIDGE MAINT |
DAN WILLIAMS COMPANY($2,271,558) |
|
0924-00-114 |
EL PASO |
EL PASO |
$4,558,404 |
VA |
C 924-00-114 |
12/06/2023 |
11/15/2023 |
PREVENT MAINT |
PMI PAVEMENT MARKING, LLC($4,800,000) |
|
0924-00-143 |
EL PASO |
EL PASO |
$584,867 |
VA |
C 924-00-143 |
02/04/2021 |
11/15/2023 |
REPLACE GUARDRAIL |
E. G. L. CONSTRUCTION, INC.($469,044) |
|
0924-00-144 |
EL PASO |
EL PASO |
$1,574,143 |
VA |
C 924-00-144 |
02/05/2021 |
11/15/2023 |
PREVENT MAINT |
BATTERSON, LLP($1,343,420) |
|
0924-00-145 |
EL PASO |
EL PASO |
$328,416 |
VA |
C 924-00-145 |
06/01/2023 |
11/27/2023 |
PREVENT MAINT |
INTERNATIONAL EAGLE ENTERPRISES, INC.($338,675) |
|
0924-00-149 |
EL PASO |
EL PASO |
$677,150 |
VA |
C 924-00-149 |
02/02/2024 |
12/22/2023 |
PREVENT MAINT |
TRI STATE ELECTRIC, LTD.($793,768) |
|
0924-06-601 |
EL PASO |
EL PASO |
$2,896,650 |
VA |
C 924-6-601 |
05/07/2020 |
11/15/2023 |
FY 2020 BRIDGE MAINT (EL PASO COUNTY) |
J.D. ABRAMS, L.P.($2,570,503) |
|
0924-06-627 |
EL PASO |
EL PASO |
$509,882 |
VA |
C 924-6-627 |
03/05/2021 |
11/15/2023 |
BRIDGE MAINT |
SCR CIVIL CONSTRUCTION, LLC($431,802) |
|
0924-06-635 |
EL PASO |
EL PASO |
$744,422 |
VA |
C 924-6-635 |
07/01/2021 |
11/15/2023 |
LANDSCAPE DEVELOPMENT |
MARTINEZ BROS. CONTRACTORS, LLC($797,516) |
|
0924-06-649 |
EL PASO |
EL PASO |
$499,042 |
VA |
C 924-6-649 |
03/04/2022 |
11/15/2023 |
PREVENT MAINT |
MIJELUM, L.L.C.($485,120) |
|
0924-06-663 |
EL PASO |
EL PASO |
$849,610 |
VA |
C 924-6-663 |
06/30/2022 |
11/15/2023 |
LANDSCAPE DEVELOPMENT |
HORIZONE CONSTRUCTION I, LTD($995,591) |
|
0924-06-689 |
EL PASO |
EL PASO |
$673,042 |
VA |
C 924-6-689 |
06/28/2023 |
11/15/2023 |
LANDSCAPE DEVELOPMENT |
INTERNATIONAL EAGLE ENTERPRISES, INC.($832,138) |
|
0924-06-700 |
EL PASO |
EL PASO |
$413,160 |
VA |
C 924-6-700 |
02/01/2024 |
12/21/2023 |
PREVENT MAINT |
HJC FARMS, INC.($458,260) |
|
0924-06-712 |
EL PASO |
EL PASO |
$1,076,196 |
VA |
C 924-6-712 |
06/05/2024 |
04/24/2024 |
PREVENT MAINT |
ROADWORX, INC. OF ILLINOIS($1,050,191) |
|
2121-04-114 |
EL PASO |
EL PASO |
$17,988,823 |
IH 10 |
CBI 2021(797) |
08/04/2021 |
11/15/2023 |
WIDEN ROAD - ADD LANES |
INTERNATIONAL EAGLE ENTERPRISES, INC.($18,039,541) |
|
0002-12-025 |
EL PASO |
EL PASO |
$631,066 |
US 62 |
CM 1702(498) |
07/11/2017 |
11/15/2023 |
OPERATIONAL IMPRVS |
TRI STATE ELECTRIC, LTD.($724,709) |
|
2121-03-154 |
EL PASO |
EL PASO |
$14,879,367 |
IH 10 |
CM 1702(689) |
08/08/2017 |
11/15/2023 |
RAMP IMPRVS |
LESNA CONSTRUCTION, INC.($16,837,592) |
|
2121-01-091 |
EL PASO |
EL PASO |
$7,890,471 |
IH 10 |
CM 2018(087) |
12/06/2017 |
11/15/2023 |
REHAB AND OPERATIONAL IMPRVS |
INTERNATIONAL EAGLE ENTERPRISES, INC.($7,550,372) |
|
0374-02-107 |
EL PASO |
EL PASO |
$850,074 |
US 62 |
CM 2019(991) |
06/05/2019 |
11/15/2023 |
OPERATIONAL IMPRVS |
INTERNATIONAL EAGLE ENTERPRISES, INC.($1,033,028) |
|
0167-01-127 |
EL PASO |
EL PASO |
$535,791 |
US 54 |
CM 2020(778) |
04/08/2020 |
11/15/2023 |
INSTL OF RVSD AND CCTVS |
TRI STATE ELECTRIC, LTD.($587,855) |
|
0002-02-055 |
EL PASO |
EL PASO |
$2,591,710 |
SH 20 |
F 2021(540) |
05/06/2021 |
11/15/2023 |
SURF/ROADWAY RESTOR |
LESNA CONSTRUCTION, INC.($2,606,598) |
|
2552-05-002 |
EL PASO |
EL PASO |
$1,214,385 |
SL 375 |
F 2021(656) |
04/07/2021 |
11/15/2023 |
HAZARD ELIM & SAFETY |
LESNA CONSTRUCTION, INC.($1,287,746) |
|
1046-01-032 |
EL PASO |
EL PASO |
$15,476,726 |
FM 659 |
F 2021(695) |
07/02/2021 |
11/15/2023 |
HAZARD ELIM & SAFETY |
J.D. ABRAMS, L.P.($14,610,296) |
|
2121-04-120 |
EL PASO |
EL PASO |
$2,929,577 |
IH 10 |
F 2021(799) |
08/05/2021 |
11/15/2023 |
INSTL ILLUM |
TRI STATE ELECTRIC, LTD.($3,267,441) |
|
2552-03-059 |
EL PASO |
EL PASO |
$2,635,073 |
SL 375 |
F 2021(800) |
08/05/2021 |
11/15/2023 |
SURF/ROADWAY RESTOR |
J.D. ABRAMS, L.P.($1,991,402) |
|
0924-00-147 |
EL PASO |
EL PASO |
$3,811,438 |
VA |
F 2021(909) |
08/05/2021 |
11/15/2023 |
ADVANCED TRAF MGT SYSTEM CONNECTION |
TRI STATE ELECTRIC, LTD.($3,567,302) |
|
2121-01-094 |
EL PASO |
EL PASO |
$181,874,297 |
IH 10 |
F 2022(053) |
02/04/2022 |
11/15/2023 |
CONSTRUCT NEW ROAD |
SUNDT CONSTRUCTION, INC.($174,305,265) |
|
2121-01-094 |
EL PASO |
EL PASO |
$192,755,434 |
IH 10 |
F 2022(053) |
10/08/2021 |
11/15/2023 |
CONSTRUCT NEW ROAD |
JORDAN FOSTER CONSTRUCTION, LLC($246,687,523) |
|
0924-06-620 |
EL PASO |
EL PASO |
$7,890,150 |
VA |
F 2022(823) |
09/07/2022 |
11/15/2023 |
CONSTRUCT PEDESTRIAN INFRASTRUCT |
TRI STATE ELECTRIC, LTD.($8,297,286) |
|
2552-03-070 |
EL PASO |
EL PASO |
$831,043 |
SL 375 |
F 2022(824) |
08/04/2022 |
11/15/2023 |
HAZARD ELIM & SAFETY |
INTERNATIONAL EAGLE ENTERPRISES, INC.($678,787) |
|
0924-00-110 |
EL PASO |
EL PASO |
$4,071,954 |
VA |
F 2023(474) |
02/01/2023 |
11/15/2023 |
PREVENT MAINT |
PMI PAVEMENT MARKING, LLC($3,850,596) |
|
0665-02-002 |
EL PASO |
EL PASO |
$20,980,783 |
SS 320 |
F 2023(613) |
04/04/2023 |
08/22/2024 |
CONSTRUCT FRONTAGE ROADS |
JORDAN FOSTER CONSTRUCTION, LLC($17,835,786) |
|
3451-01-040 |
EL PASO |
EL PASO |
$34,696,221 |
FM 1281 |
F 2023(991) |
06/27/2023 |
11/15/2023 |
INTERS IMPRV |
JORDAN FOSTER CONSTRUCTION, LLC($36,413,140) |
|
2121-02-182 |
EL PASO |
EL PASO |
$831,503 |
IH 10 |
F 2024(503) |
12/05/2023 |
11/15/2023 |
REHAB BRIDGE |
THE TRUESDELL CORPORATION($722,722) |
|
2121-02-178 |
EL PASO |
EL PASO |
$6,180,451 |
IH 10 |
F 2024(655) |
01/04/2024 |
11/23/2023 |
PREVENT MAINT |
DAN WILLIAMS COMPANY($5,680,916) |
|
0924-00-119 |
EL PASO |
EL PASO |
$4,523,278 |
VA, ETC |
F 2025(291), ETC |
12/04/2024 |
11/10/2024 |
TRAF CONTROL DEVICES |
|
|
2121-01-104 |
EL PASO |
EL PASO |
$115,716,761 |
IH 10 |
F 2B24(096) |
05/03/2024 |
03/22/2024 |
CONSTRUCT NEW ROAD |
SUNDT CONSTRUCTION, INC.($119,997,852) |
|
0001-04-102 |
EL PASO |
EL PASO |
$1,675,807 |
US 62 |
F 2B24(190) |
06/05/2024 |
04/24/2024 |
HAZARD ELIM & SAFETY |
MARTINEZ BROS. CONTRACTORS, LLC($1,541,373) |
|
0001-02-079 |
EL PASO |
EL PASO |
$3,619,662 |
SH 20 |
F 2B24(194) |
06/06/2024 |
04/25/2024 |
HAZARD ELIM & SAFETY |
TRI STATE ELECTRIC, LTD.($2,966,194) |
|
3592-01-009 |
EL PASO |
EL PASO |
$220,055,591 |
SH 178 |
F 2B24(273) |
07/09/2024 |
05/28/2024 |
INFRASTRUCT IMPRVS |
SUNDT CONSTRUCTION, INC.($243,747,771) |
|
0924-00-168 |
EL PASO |
EL PASO |
$2,125,590 |
VA |
F 2B24(396) |
08/02/2024 |
06/21/2024 |
ADVANCED TRAF MGT SYSTEM |
TRI STATE ELECTRIC, LTD.($2,231,207) |
|
6361-50-001 |
EL PASO |
EL PASO |
$79,044 |
SL0375 |
MMC - 636150001 |
07/23/2020 |
09/26/2024 |
FLEXIBLE BASE (MATERIAL ONLY) |
PASO DEL NORTE MATERIALS, LLC($77,850) |
|
6361-52-001 |
EL PASO |
EL PASO |
$122,735 |
US0054 |
MMC - 636152001 |
07/23/2020 |
09/26/2024 |
ASPHIC CONC PATCHING MATERIAL-MATERIAL ONL |
PASO DEL NORTE MATERIALS, LLC($90,900) |
|
6365-35-001 |
EL PASO |
EL PASO |
$389,250 |
IH0010 |
MMC - 636535001 |
09/02/2021 |
11/15/2023 |
DE-ICING (MATERIAL ONLY) |
NSG LOGISTICS, LLC($192,289) |
|
6365-77-001 |
EL PASO |
EL PASO |
$279,870 |
SL0375 |
MMC - 636577001 |
09/17/2020 |
11/15/2023 |
DE-ICING/ANTI-ICING (MATERIAL ONLY) |
DIGG COMMERCIAL, LLC($327,750) |
|
6365-78-001 |
EL PASO |
EL PASO |
$1,000 |
US0054 |
MMC - 636578001 |
10/22/2020 |
11/15/2023 |
LIME (MATERIAL ONLY) |
E.V.G. ENTERPRISE($7,500) |
|
6365-81-001 |
EL PASO |
EL PASO |
$20,250 |
IH0010 |
MMC - 636581001 |
07/23/2020 |
09/26/2024 |
SAND (MATERIAL ONLY) |
JOBE MATERIALS, L.P.($16,650) |
|
6365-83-001 |
EL PASO |
EL PASO |
$44,522 |
US0054 |
MMC - 636583001 |
09/17/2020 |
11/15/2023 |
AGGREGATE (GR5) (MATERIALS ONLY) |
PASO DEL NORTE MATERIALS, LLC($41,500) |
|
6365-88-001 |
EL PASO |
EL PASO |
$242,500 |
IH0010 |
MMC - 636588001 |
09/16/2021 |
11/15/2023 |
DE-ICING (MATERIALS ONLY) |
NSG LOGISTICS, LLC($163,346) |
|
6365-88-001 |
EL PASO |
EL PASO |
$5,420 |
SL0375 |
MMC - 636588001 |
10/27/2020 |
11/15/2023 |
HYDRAULIC CEMENT (MATERIALS ONLY) |
TOUCHSTONE RESOURCES, LLC($10,960) |
|
6368-20-001 |
EL PASO |
EL PASO |
$96,425 |
US0054 |
MMC - 636820001 |
10/27/2020 |
11/15/2023 |
DE-ICING/ANTI-ICING (MATERIAL ONLY) |
THE BARGAIN SOURCE($65,800) |
|
6372-07-001 |
EL PASO |
EL PASO |
$722 |
US0054 |
MMC - 637207001 |
11/12/2020 |
11/15/2023 |
CONC REPAIR MATERIAL (MATERIAL ONLY) |
MESA D CORP.($8,100) |
|
6374-46-001 |
EL PASO |
EL PASO |
$11,570 |
IH0010 |
MMC - 637446001 |
12/10/2020 |
11/15/2023 |
LIME (MATERIALS ONLY) |
MESA D CORP.($13,383) |
|
6383-96-001 |
EL PASO |
EL PASO |
$272,500 |
IH0010 |
MMC - 638396001 |
08/31/2021 |
11/15/2023 |
HOT MIX |
JOBE MATERIALS, L.P.($246,000) |
|
6385-08-001 |
EL PASO |
EL PASO |
$114,000 |
SL0375 |
MMC - 638508001 |
08/26/2021 |
11/15/2023 |
AGGREGATE |
JOBE MATERIALS, L.P.($63,465) |
|
6388-39-001 |
EL PASO |
EL PASO |
$80,000 |
US0054 |
MMC - 638839001 |
09/28/2021 |
11/15/2023 |
ASPHIC PATCHING MATERIAL |
MESA D CORP.($110,175) |
|
6389-41-001 |
EL PASO |
EL PASO |
$60,000 |
SL0375 |
MMC - 638941001 |
11/09/2021 |
11/15/2023 |
SAND (MATERIAL ONLY) |
JOBE MATERIALS, L.P.($69,401) |
|
6392-44-001 |
EL PASO |
EL PASO |
$614,250 |
FM2637 |
MMC - 639244001 |
11/03/2021 |
11/15/2023 |
AGGREGATE (MATERIAL ONLY) |
JOBE MATERIALS, L.P.($273,001) |
|
6392-92-001 |
EL PASO |
EL PASO |
$107,600 |
SL0375 |
MMC - 639292001 |
12/07/2021 |
11/15/2023 |
FLEXIBLE BASE (MATERIAL ONLY) |
JOBE MATERIALS, L.P.($107,050) |
|
6392-93-001 |
EL PASO |
EL PASO |
$389,715 |
FM2637 |
MMC - 639293001 |
12/02/2021 |
11/15/2023 |
EMULSION - MATERIAL ONLY FOR FM2637 |
ERGON ASPHALT & EMULSIONS, INC.($461,623) |
|
6401-28-001 |
EL PASO |
EL PASO |
$149,000 |
SL0375 |
MMC - 640128001 |
05/10/2022 |
11/15/2023 |
AGGREGATE |
TOUCHSTONE RESOURCES, LLC($142,500) |
|
6405-06-001 |
EL PASO |
EL PASO |
$17,800 |
IH0010 |
MMC - 640506001 |
06/21/2022 |
11/15/2023 |
LIME |
TOUCHSTONE RESOURCES, LLC($14,240) |
|
6405-20-001 |
EL PASO |
EL PASO |
$15,000 |
IH0010 |
MMC - 640520001 |
06/21/2022 |
11/15/2023 |
HYDRAULIC CEMENT |
TOUCHSTONE RESOURCES, LLC($15,000) |
|
6409-65-001 |
EL PASO |
EL PASO |
$313,495 |
IH0010 |
MMC - 640965001 |
06/30/2022 |
11/15/2023 |
DE-ICING SALT |
NSG LOGISTICS, LLC($312,266) |