6367-68-001 |
CARSON |
AMARILLO |
$37,200 |
FM0293 |
MMC - 636768001 |
09/09/2020 |
11/15/2023 |
FLEXIBLE BASE (MATERIALS ONLY) |
L A FULLER & SONS CONSTRUCTION, LTD.($31,860) |
|
2218-01-035 |
CARSON |
AMARILLO |
$4,863,894 |
FM 2373 |
BR 1902(241) |
10/02/2019 |
11/15/2023 |
REPLACE BRIDGE AND APPROACHES, RELOCATE RAMP |
J. LEE MILLIGAN, INC.($5,732,296) |
|
0753-02-022 |
CARSON |
AMARILLO |
$735,917 |
FM 293 |
STP 2020(739)HES |
06/05/2020 |
11/15/2023 |
SFT - SAFETY IMPRV PROJECTS |
L A FULLER & SONS CONSTRUCTION, LTD.($799,569) |
|
6463-69-001 |
CARSON |
AMARILLO |
$446,500 |
IH0040 |
RMC - 646369001 |
04/04/2024 |
02/20/2024 |
MOW HWY RIGHT OF WAY |
BERT WHITAKER($434,933) |
|
6375-14-001 |
CARSON |
AMARILLO |
$254,300 |
IH0040 |
MMC - 637514001 |
03/11/2021 |
11/15/2023 |
HMAC PICKUP/DELIVERY(MATERIALS ONLY) |
RK HALL, LLC($268,300) |
|
6374-98-001 |
CARSON |
AMARILLO |
$274,724 |
IH0040 |
MMC - 637498001 |
03/11/2021 |
11/15/2023 |
SURF TREATMENT AGG(MATERIAL ONLY) |
VOLCANIC STONE CO.($274,195) |
|
6395-92-001 |
CARSON |
AMARILLO |
$292,900 |
IH0040 |
MMC - 639592001 |
02/10/2022 |
11/15/2023 |
SEAL COAT |
VOLCANIC STONE CO.($332,334) |
|
6312-12-001 |
CARSON |
AMARILLO |
$522,440 |
IH0040 |
BPM - 631212001 |
03/08/2017 |
11/15/2023 |
MISC. BRIDGE REPAIRS |
GILVIN-TERRILL, LTD.($430,115) |
|
6398-12-001 |
CARSON |
AMARILLO |
$676,843 |
IH0040 |
RMC - 639812001 |
04/07/2022 |
11/15/2023 |
MOW HWY RIGHT OF WAY |
BERT WHITAKER($900,565) |
|
6398-12-001 |
CARSON |
AMARILLO |
$415,840 |
IH0040 |
RMC - 639812001 |
06/29/2022 |
11/15/2023 |
MOW HWY RIGHT OF WAY |
BERT WHITAKER($519,383) |
|
6397-66-001 |
CARSON |
AMARILLO |
$299,495 |
IH0040 |
MMC - 639766001 |
04/13/2023 |
11/15/2023 |
AGGREGATE |
VOLCANIC STONE CO.($325,202) |
|
6420-21-001 |
CARSON |
AMARILLO |
$339,820 |
IH0040 |
RMC - 642021001 |
11/03/2022 |
11/15/2023 |
CABLE MEDIAN BARRIER SYSTEM REPAIR |
BK FIELD OPERATIONS LLC($355,464) |
|
6435-60-001 |
CARSON |
AMARILLO |
$4,845,000 |
IH0040 |
RMC - 643560001 |
04/05/2023 |
11/15/2023 |
MILL AND INLAY |
J. LEE MILLIGAN, INC.($5,263,125) |
|
6382-55-001 |
CARSON |
AMARILLO |
$240,150 |
IH0040 |
MMC - 638255001 |
09/14/2021 |
09/24/2024 |
WINTER WEATHER MATERIAL |
SOUTHWEST ENVIROTX PARTNERS, LLC($189,675) |
|
6469-03-001 |
CARSON |
AMARILLO |
$3,388,725 |
IH0040 |
RMC - 646903001 |
07/09/2024 |
06/04/2024 |
MILL AND INLAY |
J. LEE MILLIGAN, INC.($4,669,500) |
|
0275-02-070 |
CARSON |
AMARILLO |
$2,193,085 |
IH 40 |
STP 2020(509)HES |
01/10/2020 |
09/26/2024 |
INSTL MEDIAN BARRIER |
GRATIOT CONSTRUCTION, LTD.($1,652,413) |
|
0275-04-069 |
CARSON |
AMARILLO |
$5,701,286 |
IH 40 |
STP 2B23(012)TAPS |
08/03/2023 |
11/15/2023 |
TRANSPORT NON-ROADWAY |
J. LEE MILLIGAN, INC.($6,318,690) |
|
0275-03-066 |
CARSON |
AMARILLO |
$16,161,505 |
IH 40 |
NH 2019(053) |
09/07/2018 |
11/15/2023 |
EBL - MILL, REHAB AND OVERLAY |
GILVIN-TERRILL, LTD.($15,103,094) |
|
0275-04-061 |
CARSON |
AMARILLO |
$14,893,249 |
IH 40 |
BR 2024(461) |
12/05/2023 |
11/15/2023 |
BRIDGE MAINT |
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC($13,665,831) |
|
0275-04-052 |
CARSON |
AMARILLO |
$7,990,543 |
IH 40 |
C 275-4-52 |
01/09/2019 |
11/15/2023 |
ACP OVERLAY,CRCP REPAIR, MBGF, AND STRIPING. |
KIEWIT INFRASTRUCTURE SOUTH CO.($8,012,745) |
|
6471-72-001 |
CARSON |
AMARILLO |
$1,138,419 |
SH0207 |
MMC - 647172001 |
09/05/2024 |
07/25/2024 |
AGGREGATE |
VOLCANIC STONE CO.($1,126,552) |
|
0455-02-027 |
CARSON |
AMARILLO |
$8,924,621 |
SH 152 |
BR 2021(709) |
07/01/2021 |
11/15/2023 |
BRIDGE REPL |
GILVIN-TERRILL, LTD.($8,225,270) |
|
0455-02-031 |
CARSON |
AMARILLO |
$17,731,103 |
SH 152 |
F 2B23(295) |
11/02/2023 |
11/15/2023 |
HWY IMPRV |
RK HALL, LLC($16,474,504) |
|
0356-02-048 |
CARSON |
AMARILLO |
$1,133,460 |
SH 207 |
STP 2020(635) |
03/04/2020 |
11/15/2023 |
REPLACE EXIST LIFT STATION |
L A FULLER & SONS CONSTRUCTION, LTD.($1,042,468) |
|
6375-13-001 |
CARSON |
AMARILLO |
$163,467 |
US0060 |
MMC - 637513001 |
03/11/2021 |
11/15/2023 |
LIMESTONE ROCK ASPH(MATERIALS ONLY) |
VULCAN CONSTRUCTION MATERIALS, LLC($160,164) |
|
6337-63-001 |
CARSON |
AMARILLO |
$125,130 |
US0060 |
RMC - 633763001 |
09/26/2018 |
11/15/2023 |
CLEANING AND SWEEPING HWYS |
PANHANDLE SWEEPING & MAINTENANCE, LLC($107,750) |
|
6469-89-001 |
CARSON |
AMARILLO |
$432,740 |
US0060 |
MMC - 646989001 |
08/01/2024 |
06/24/2024 |
HYDRAULIC CEMENT |
TOUCHSTONE RESOURCES, LLC($387,690) |
|
6446-80-001 |
CARSON |
AMARILLO |
$2,653,155 |
US0060 |
MMC - 644680001 |
08/02/2023 |
11/15/2023 |
ASPH |
ERGON ASPHALT & EMULSIONS, INC.($2,240,881) |
|
6461-55-001 |
CARSON |
AMARILLO |
$1,514,589 |
US0060 |
MMC - 646155001 |
01/04/2024 |
11/23/2023 |
AGGREGATE |
HOWELL SAND COMPANY, INC.($1,429,382) |
|
6372-01-001 |
CARSON |
AMARILLO |
$290,825 |
US0060 |
MMC - 637201001 |
10/20/2020 |
11/15/2023 |
I&II SALT(MATERIALS ONLY) |
UNITED SALT CORPORATION($304,583) |
|
0169-03-036 |
CARSON |
AMARILLO |
$17,852,193 |
US 60 |
NH 2019(080) |
10/03/2018 |
11/15/2023 |
EBL - FULL DEPTH REPAIR, MILL AND FILL |
RK HALL, LLC($16,196,034) |
|
0169-05-041 |
CARSON |
AMARILLO |
$15,490,402 |
US 60 |
NH 2013(613) |
02/06/2019 |
11/15/2023 |
REHAB EXISITNG ROADWAY |
RK HALL, LLC($16,325,738) |
|
0169-04-036 |
CARSON |
AMARILLO |
$15,322,422 |
US 60 |
NH 2013(611) |
10/04/2017 |
11/15/2023 |
FULL DEPTH RECLAMATION,PLANING,HOTMIX&PAV MRK |
RK HALL, LLC($11,057,967) |
|
0169-05-042 |
CARSON |
AMARILLO |
$12,655,032 |
US 60 |
NH 2013(614) |
02/02/2018 |
11/15/2023 |
REHAB EXIST ROADWAY |
RK HALL, LLC($10,873,603) |
|
0169-03-039 |
CARSON |
AMARILLO |
$3,049,160 |
US 60 |
STP 2022(502)HES |
05/05/2022 |
08/31/2024 |
HWY IMPRV |
HJC FARMS, INC.($3,699,105) |